Casesolutions09 (1) Pert Coleman

Solutions to Case Problems Chapter 9 Project Scheduling: PERT/CPM Case Problem:  R.C. Coleman 1. R.C. Coleman's Projec

Views 69 Downloads 0 File size 372KB

Report DMCA / Copyright

DOWNLOAD FILE

Recommend stories

Citation preview

Solutions to Case Problems

Chapter 9 Project Scheduling: PERT/CPM Case Problem:  R.C. Coleman 1.

R.C. Coleman's Project Network

D

A Start

C B

E

F

G

Activity A B C D E F G H I J K

Activity A B C D E F G H I J K

I

Earliest Start  0  0  9 13 13 23 13 29 29 35 39

K H

J

Expected Time  6  9  4 12 10  6  8  6  7  4  4 Latest Start  3  0  9 17 13 23 21 29 32 35 39

Earliest Finish  6  9 13 25 23 29 21 35 36 39 43

CP - 51

Finish

Variance 0.44 2.78 0.44 7.11 1.00 0.44 7.11 0.44 2.78 0.11 0.44 Latest Finish  9  9 13 29 23 29 29 35 39 39 43

Slack 3 0 0 4 0 0 8 0 3 0 0

Critical Activity Yes Yes Yes Yes Yes Yes Yes

Chapter 9

The expected project completion time is 43 weeks.  The critical path activities are B­C­E­F­H­J­K.   The variance of the critical path is 5.67.                                40  43 z  1.26 5.67 Area = 0.3962 P(T  40) = 0.5000 ­ 0.3962 = 0.1038  Given the above calculations, we can conclude that there is about a 10% chance that the project can  be completed in 40 weeks or less.  Coleman should consider crashing project activities. 2.

20% 80%

Planned project completion time

Desires 40-week completion time

For 80% chance, z = +0.84 Thus 40  E (T ) 5.67

 0.84

Solve for E(T) = 38 weeks. R.C. Coleman should crash activities to reduce the expected project completion time to 38 weeks. 3.

In this section, we will use expected activity times as normal times and use a linear programming  model based on expected times to make the crashing decisions. Let

xi = the completion time for activity i yi = the amount of crash time for activity i

CP - 52

Solutions to Case Problems

Min 450yA  +  400yB  +  600yC  +  300yD  +  1000yE  +  550yF  +  750yG  +  700yH  +  800yI  + 400yJ  +   500yK s.t. xA + yA    6

xK    38

xB + yB     9

yA    2 

xC + yC – xA    4

yB    2 

xC + yC – xB    4

yC    2 

xD + yD – xC    12

yD    4 

xE + yE – xC    10

yE    3 

xF + yF – xE    6

yF    2 

xG + yG – xC    8

yG    3

xH + yH – xF    6

 

yH    2

xH + yH – xG    6

yI    3

xI + yI – xD    7

yJ    1

xI + yI – xF    7

yK    1

xJ + yJ – xH    4

All xi,yi    0

xK + yK – xI    4 xK + yK – xJ    4 The optimal crashing decisions are as follows: Crash Activity B F J K

Weeks 2 1 1 1 Total 

CP - 53

Cost  800  550  400  500 2250

Chapter 9

A revised activity schedule based on these crashing decisions is as follows: Activity A B C D E F G H I J K

Earliest Start 0 0 7 11 11 21 11 26 26 32 35

Latest Start 1 0 7 14 11 21 18 26 28 32 35

Earliest Finish 6 7 11 23 21 26 19 32 33 35 38

Latest Finish 7 7 11 26 21 26 26 32 35 35 38

Slack 1 0 0 3 0 0 7 0 2 0 0

Critical Activity Yes Yes Yes Yes Yes Yes Yes

The student should comment on the fact that the crashing decisions may alter the variance in the  project completion time.  By defining revised optimistic, most probable, and pessimistic times for  crashed activities B, F, J, and K, a revised variance in the project completion time can be found.   Using this result, a revised probability of a 40­week completion time can be computed.

CP - 54