June 2014 PRESSURE RELIEF SYSTEMS Acknowledgment DEDICATED TO: API STD - RP 520/ 521/ 526/ 537 Various Client/ Projec
Views 91 Downloads 5 File size 754KB
June 2014
PRESSURE RELIEF SYSTEMS Acknowledgment
DEDICATED TO:
API STD - RP 520/ 521/ 526/ 537 Various Client/ Project Standards/ Specifications Pictures from many sources, suppliers, internet
My friend Winston Yeo, KBR, Singapore/ Chevron, Thailand
Topics Introduction Relief Devices Codes & Standards Relieving Scenarios (Demands) & Loads Sizing Installation Isolation Design Features
PSV
Introduction
PAHH PIC/PAH NOP
Control system maintains stable operation Trip / shutdown system provides primary protection,
when control system fails Relief system provides secondary protection, when control and trip systems fail – ultimate protection or last line of defence PIC
T0 Flare PAHH PALL
T0 Compressor SDV
Well Fluids SDV
Production Separator SDV SDV
RV lifting: a serious incident
Oil/ Condensate Produced Water
Code Vs Recommended Practice Relief devices – key part of plant Layer of Protections to protect plant and personnel. Prevent production loss Relief devices are required by national codes and standards, mandated under law
Community Emergency Response Emergency, Evacuation Plant Emergency Response Containment/ Evacuation Procedure Mitigation Mechanical mitigation, Relief System Operator Action Prevention SIS Trips Operator Response Controls & Monitoring Controls, Alarms Operator Supervision
Process
ASME is a Code. Compliance is mandatory. API is a recommended practice. API is also getting adopted as a National / International Standard
Where Pressure Relief is not possible The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Fast chemical reactions: Pressure propagation rate is very high and loss of
containment may occurs before RV pops. “hot spots,” decompositions & internal detonation/fires Relieving rate requires large relief areas
Plugging, polymerization or deposition that may
partially or completely block RV Relieved chemicals may polymerize and plug. PSV useless
Multi-phase relief: where rate is difficult to predict Relief may create additional hazards due to stack
location or very large vent/ flare system Use HIPPS
Relief Scenarios
Tank drained. Pulled vacuum The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. TheThe link ed file image may hav cannot e been bemov display ed, ed. renamed, The file ormay deleted. hav eVerify been mov that the ed, link renamed, pointsor to deleted. the correct Verify filethat and the location. link points to the correct file and location.
Air freshener can in a closed car - Thermal The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Vacuum column fire
Column internals - Pyrophoric fire The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Semi sub – what was left
RELIEF DEVICES
Relief
Devices The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Relief Valves Rupture Disks The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Rupture Pins Buckling Pins PVRV Blow-off Hatches Explosion Doors
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Relief Devices The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
This image cannot currently be display ed. This image cannot currently be display ed.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Relief Valves Conventional Balanced Pilot
This image cannot currently be display ed.
Conventional RV
Set Press
Most common Simple, cheap and reliable Backpressure reduces capacity Variable back pressure limited to 10% of set pressure Large spring required limits set pressure of bigger PSV Constant or superimposed backpressure increases set Why? point on a 1 for 1 basis 150# RV Set Press, psig at 100°F
100
0 Back Press
50
D–P
Q
R
T
285
165
100
65
This image cannot currently be display ed.
Balanced Bellows RV
Not allowed per ASME section I Back pressure max 30% on all except smaller sizes. Up to 50% with capacity correction Fragile bellows. Mechanical limit imposed by bellows Bellows can plug; movement restricted In plugging and polymerizing service Bellows sealed in hydrate, solid, foaming and coking services to keep foreign matter out of bonnet Bellows prone to fatigue and pin-hole leaks. [Leaks take away ability to handle backpressure; hence bonnet is vented. As long vent is bigger than “holes” OK.] Bonnet vent must be routed to safe location in toxic service Why?
Bellows original purpose was to protect the spindle & guide from corrosive fluids. Beyond 30% back pressure, lift and hence capacity affected
Balanced Disk RV This image cannot currently be display ed.
Backpressure acting on top and
bottom of disk cancels each other Backpressure ha no effect on RV opening or closing pressure
Set Press
This image cannot currently be display ed.
100 RV Opening Pressure RV Reseating Pressure 0 Back Press
50
Pilot RV Process pressure on a differential area piston keeps the seat closed Pilot: A small PSV that pops and removes piston top pressure,
allowing the main valve to open
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the
Pilot
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Pilot Dome Dome
Piston
Pilot Tube Pilot Tube Note: Piston top area > bottom area. For the same pressure, force on top > force on bottom, keeping the seat closed
More on Pilot RV Process pressure on the larger piston (top) area opposes
pressure on the smaller seat, keeping the valve shut Higher the process pressure, greater the downward force, keeping the seat tightly closed. c.f spring loaded RV A small auxiliary relief valve (pilot) controls the main RV. It pops open relieving top pressure, opening main RV Larger RVs can have higher set pressures; no longer limited by spring force. c.f spring loaded RV Full lift and capacity achieved near set pressure as there is no heavy spring load to overcome With pop action, full lift at set pressure; with modulating pilot, full lift at relieving pressure; modulating pilot relieves only what is required
More on Pilot The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Pilot is a small RV! 1. As process pressure reaches set pressure, the spring is compressed; lower feeding seat closes, isolating process gas 2. Upper seat opens, venting gas and pressure in dome; and opening RV Process gas isolated during a relief – no flow pilot Flowing pilot, discharges process gas before, during and after a relief. Not recommended
2 1
Flowing design may lead to freezing or particulates into the pilot Based on one-shot venting or gradual venting “pop” or “modulating” action “Pop” or fast action is for rapid relief of gas. Recommended. Spring loaded RV
Spindle travel - decides blowdown. 3% blowdown possible
“Modulating” allows RV opening with a small pressure rise; fast response. Relieves what is reqd. Diaphragm RV
More on Pilot RV Most have soft seats; remote sensing capability – pilot
tube intake need not be at RV inlet Polymerizing, plugging service, sensing line can plug. Use non-flow type or filtered sensing line in dirty service Backpressure: Set pressure not affected unless pilot is vented to header Caution: Higher backpressure can lead to reverse flow and product contamination, during start-up and shutdown. Use check valve Usual to have no-flow, pop action elastomer seat/ seal type. Less commonly used. May require prior approval Liquid filled systems: Blowdown may change c.f gas service. Operating time too rapid producing water hammer or too slow. Pilot affected by particulate contamination or corrosion
Capacity - Back Pressure Impact RV: ‘Nozzle’ or ‘orifice’ flow decided by:
Transition Point Sonic to Sun-sonic
upstream pressure, as long
as it is ‘critical’ or ‘sonic’ ∆P, Pressure drop (P1-P2), if sub-sonic
Back-pressure adds to spring force, reduces lift and flow (‘capacity’ of RV)
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Back Pressure - Conventional RV The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Backpressure affects lift; impacts capacity severely At 15% valve fully closed The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Back Pressure - Balanced Bellows Bellows nullify backpressure effect to an extent The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
At 30% capacity reduced The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Difficult to have small bellows. Size D & E, may be a ‘modified’ F !! Bellows fixed at at upper end. High back pressure lengthens the bellows at the lower end, restricting seat lift
Back Pressure - Balanced Disk RV Disk nullify backpressure effect to an extent At 30% capacity reduced
At 20% capacity reduced The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Balanced Spindle type can withstand higher backpressure; Sizes to 2J3 only
Back Pressure - Pilot RV Flow Flow follows closely nozzle flow For k = 1.3 & BP = 70%. Flow:
Nozzle = 92% Pilot = 78% Back flow Preventer:
Backpressure may open the main valve when process pressure is low as at start-up. May contaminate products. C3 Refrigeration
Back Pressure Impact - Comparison Set Pressure Vs Lift The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Conventional This image cannot currently be display ed.
Pilot
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Backpressure Impact - Tests University of Milan Test on 5 Balanced RV, 2 J 3 Supposed to be good to 50% BP viz k = 1 Capacity Lost, %
at BP, %
Remarks
A
10
50
B
30
50
C
40
30
D
20
30
0% at 32%
E
60
18
bellow ruptured
This image cannot currently be display ed.
This image cannot currently be display ed. This image cannot currently be display ed. This image cannot currently be display ed.
Terminology - Refresher Relief Valve: Valve opens in proportion to
overpressure. Liquid (incompressible fluids) service Safety Valve: Valve opens rapidly with pop action. Vapour (compressible fluids) service Safety Relief Valve: Either a safety or relief valve Pressure Relief Valve: Generic term for all of above
Terminology - Refresher MAWP: Max Allowable Working Pressure on top of vessel
based on wall thickness provided at coincident temperature. ≈> Design Pressure Design Pressure: Equipment/ system design pressure at design temperature Set Pressure: Pressure at which RV is set to open. May be same or less than Design Pressure Overpressure: Pressure increase over set pressure Relieving Pressure: Set pressure + Overpressure Accumulation: Pressure increase over MAWP Back pressure: Pressure at the outlet flange/ pressure in discharge system Where RV is set below MAWP, overpressure can be higher to match MAWP + Accumulation
Terminology - Refresher V-002
Superimposed back pressure - Affects set pressure.
Pressure at outlet flange before RV opens
E-001
Constant superimposed BP: Always the same pressure. When RV
discharges to a closed system. Can be high ~ 50% of set pressure. Variable superimposed BP: Varies based on flow from other sources. When multiple sources discharge to a common header
Built-up back pressure - Does not affect set pressure but
affects capacity Pressure that develops in the discharge header as a result of flow thru RV
Total back-pressure = Superimposed + Built-up BP Spring differential: Difference between set pressure and
Why?
superimposed constant BP. It is not wise to give a superimposed constant BP in a data sheet unless one exists.
Back Pressure - Example Flare Stack
Normal Operating Press = 0.3 U
Flare Header
∆P = 10 U due to flow from this + other PSVs SP = 100 Units Relief valve
∆P = 5 U
Care needed while specifying constant BP
Superimposed Constant Back Press = 0.3 U Built-up Back Pressure = 15 U Total Back Pressure = 15.3 U Spring Differential (Set Pressure – Constant BP) Spring set at: = 99.7 U
Flare Knockout Drum
Back Pressure - More Info Backpressure adds to spring load, prevents full
Size
lift
Flow and backpressure reduced; Valve opens again Close Open. Rapid cycling or chattering
P1, backpressure at valve outlet flange is
known and NOT PB inside the valve at nozzle outlet Bigger the RV, smaller is Outlet: PSV area (Ao/A) ratio; Higher is PB PB, controls flow in sub-sonic cases Vendors have come up with a correction factor to Nozzle Coefft, to account for this – based on valve body / nozzle geometry The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Design Tip: Backpressure mechanical limit on RV is decided by bellows. Bigger the RV lower is allowable backpressure. Affects non-flowing RVs too; forgotten by Process Engineers. See RP 526
P2 PB
Outlet: PSV Area Ratio Area, in2 (Ao/A)
1½ D 2
0.110 (31)
1½ E 2
0.196 (17)
1½ F 2
0.307 (11)
2G3
0.503 (15)
2H3
0.785 (9)
3J4
1.287 (10)
3K4
1.838 (7)
3L4
2.853 (5)
4M6
3.600 (8)
4N6
4.340 (7)
4P6
6.380 (5)
6Q8
11.050 (5)
6R8
16.000 (3)
8 T 10
26.000 (3)
Terminology - Refresher Blowdown: Difference between set pressure and reseating
pressure, % of set pressure. Usually 3% Cold differential test pressure: Set pressure with correction for backpressure and/or temperature service condition Simmer: Audible or visual release of fluid across the RV just prior to opening at set pressure. Excessive simmering is detrimental to valve seating surfaces Chattering: Rapid opening and closing of RV in quick succession. Wear and tear on seating surfaces leading to leak in normal operation. Caused by:
Oversized RV Inlet loss > 3% Excessive back-pressure Broken or leaking balanced bellows
Lift: Rise of the disc to open the RV
RV Operation - Refresher
Boiler Board Formula with Lift
As the seat lifts,
S Seat Disk Curtain Lift, L
flow is thru (i) nozzle at full lift or (ii) curtain for partial lift Nozzle Area = πD²/4 Curtain Area = πDL; L = D/4 Usual lift is about 35 to 40% At PSV opening point, press * area = spring load To reach full lift, additional overpressure required, say 10% to compress the spring. Not enough. Solution? Add a skirt to seat, to add ‘area’ and redirect flow to add to lift Blowdown Ring, controls blowdown Top: Short Simmer; long blowdown
P
Skirt
Increases Decrease Blowdown
Nozzle Diameter, D Blowdown Ring
RV Operation - Refresher This image cannot currently be display ed.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Rupture Disks Non-reclosing
Non-reclosing: Unlike a PSV that closes once the pressure < set pressure, RDs remain open and discharge the contents. It has to be replaced after an event
Good for large relief; instantaneous and unrestricted relief For valuable/ toxic fluids (no leak) and viscous, high melting
point fluids For corrosive and slurry (no exposed seat/ spring) Used upstream and downstream of RV in corrosive services Upstream of RV
Protects RV internals from corrosion – save $$ using standard MOC; Prevents leakage thru RV; Prevents plugging and gumming of RV; Allows in-situ calibration testing of RV Downstream of RV Note: Max distance between RD and PSV = 5D Protects RV internals from corrosion – save $$ using standard MOC; Check leakage thru RV; Prevents fouling and gumming of RV; Cushions impact of variable backpressure In parallel to or in series with RV Design Tip: RD + RV requires Combined Capacity Factor ≈ 0.9 factor on RV area; combined inlet ∆P E-001 tube side design pressure. Relief rate: Based on pump head at PSV-001 relieving pressure and max suction pressure of pump P- 001 Good design to have pump outlet designed for shut-off head
V-001
Capacity
Relief flow is less than Operating flow
Blocked Outlet To satisfy ASME, a PSV
Relieving
Operating Head
is required on equipment at pump outlet, even if its design pressure > pump shutoff pressure Relief rate may be nominal or Nil. If a PSV is provided for some other reason, say fire, then it will do
Capacity
Pump suction valve & piping downstream of it to suit discharge conditions
Control Valve Failure Causes
Instrument air failure; Signal (wiring) failure; DCS hardware/software failure Improper manual operation by operator Mechanical malfunction of control valve Hand wheel left engaged on control valve Plugging
Evaluate both Open and Closed position of control valve No credit: for interlocks / Emergency Shutdown System in RV size;
Credit may be taken for total load to flare header Credit may be taken for normally open flow paths and not affected Simultaneous failure control valve and bypass: Owner preference
Options: No bypass; RO in bypass; bypass valve Cv same as control valve; parallel but not-connected control valve; parallel control valve on its own
Control Valve Failure PSV - 002
LCV - 1 fails open
PSV - 001
PSV - 002 Size:
Max flow thru LCV-1 minus V-2 normal flow Max flow thru LCV-1: Max Cv + downstream PSV - 002 relieving pressure + ∆P between LCV and PSV
LCV – 1 fails closed
SDV-2 V-2 V-001 SDV-1 SDV-3 LCV-1 V-002
L-2
PSV - 001 Size: Blocked
outlet
Note: Several approaches to gas blowby load estimation: All gas; gas volume equivalent volume of liquid; both gas and liquid limited to max inflow etc. Dynamic Simulation helps get realistic results If it overloads or is the largest LP Flare load, consider same design pressure for the d/s vessel to eliminate gas blowby case
Heat Exchanger Tube Failure
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Shell & Tube heat exchangers tubes
may fail due to thermal shock, vibration, corrosion etc No PSV, if high pressure side design/ operating pressure is ≤130% of design (= hydrotest) pressure of low pressure side * temperature correction 130% or ‘0.77 rule’ does not mean tubes don’t rupture – a common mistake Evaluate potential overpressure of connected equipment Evaluate potential chemical reactions when two sides mix
2 Options - tube failure at mid tube viz 2 orifices and
failure at tube sheet viz 1 nozzle + 1 orifice For PCHEs, one full channel failure No PSV for tube failure in double pipe exchangers
Heat Exchanger Tube Failure The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Credit: Flow thru normally open path if LP fluid is gas or vapour If LP side is liquid, pressure build-up to push and
accelerate large liquid mass. It is as good as blocked
Some consider tube rupture only when HP to LP differential pressure > 65 bar (1,000 psi) On tube rupture, pressure spike is rather quick. Usually rupture disks are provided as spring loaded RVs take time to react Opening time: Rupture pin: 2ms; Rupture disk: 5ms; RV
25ms Recommended to have 2 RDs at either end of LP side Dynamic Simulation studies help, select location
Check Valve Failure All valves leak or pass. In early designs check valve leak was
NOT considered
Check valves stop “bulk” flow but can’t avoid leak past them Some considered check valve leak only in high pressure or dirty or
surging service. Some considered specially designed, power assisted check valve can stop reverse flow. No longer valid
No credit to single check valve. Reduced flow area for 2
dissimilar check valves
Standard calculation methods available to estimate leak past a
check valve Note: Along with leak, pressure is transmitted. That is HP side can pressurize LP side shut-in This point out is missed out by Process Engineers in a Hazop review
When a compressor trips, discharge from other running compressors can back flow into the tripped one, pressurizing its Suction Drum
Check Valve Failure At a common manifold, when one of the stream stops
flowing or a pump/ compressor feeding it stops, fluids from other streams may back flow thru the non-flow pipe
Header A
Xmas Tree
Well
3 Workers Killed Header B
Test Header
Wellhead inlet manifolds: A common check valve or one per header
Thermal Expansion Liquid filled equipment / piping that is blocked-in and heated Solar radiation; Hot side of exchanger; Heat tracing
Heat Exchangers: Cold side vapor pressure > design pressure At ambient temperature; At hot side fluid inlet temperature; Heat
tracing
OSBL: Yard piping 10% overpressure for vessels and 33% for piping CSO or LO valves can eliminate thermal PSV, provided Owner
agrees to administrative control
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Air freshener can in a closed car - Thermal
Thermal Expansion Thermal Expansion Massive Force Liquid Ammonia Tank in a closed garage, exploded and
propelled the truck 40m
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
External Fire Vacuum column fire
Pool fire under equipment, even if contents are not flammable Radiant + direct heat boils liquid / expands vapour increasing
pressure Equipment assumed blocked in and isolated when fire occurs and inflow stopped
There can be exemptions for this rule, example, heat exchangers
ASME stamped equipment must be protected unless fire can be
ruled out or equipment/ system cannot be blocked-in Piping and piping components do not require protection.
Interconnecting piping included in adjacent equipment
Equipment grouping: 8.6m (28.2’) radius (2,500 sq.ft area) and 7.6m
(25’) high from grade are grouped in a single fire zone
Liquid at NLL or HLL
Evaluate: Effects of chemical reaction, fluid decomposition and fluid
behaviour (foaming, frothing, etc.)
Do NOT design for Jet Fire load as some do. As API RP 521 says, jet fires are handled by blowdown viz. removing fuel
Design Tip: API indicates max fire zone size. Use it wisely to reduce Blowdown load + Flare size
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
External Fire
Caution: Corrosion under insulation can bring a vessel down before fire does!. Need Inspection windows
Fire NOT considered if: Sloping or proper drainage eliminates pool fire possibility No flammable hydrocarbon exists in the area Air Coolers/ equipment located 7.6m (25’) above grade OR
over open grating If fire load is relieved thru any passage that can’t be shut If Owner instructs: “Equipment will be vented and drained when taken out of service”. e.g. Pig launcher/ receiver
Credit for fireproof insulation as allowed by API; it
should withstand firewater jet impact Gas vessel: Fire PSV not effective as vessel metal temperature > Creep temperature PETRONAS: No fire PSV for gas vessels Design Tip: If fire relief temperature > equipment design temperature, use design temp for RV material and flange selection. Say so in data sheet. Vessel metal temperature will be 200-300°C > RV relief temperature. Vessel will fail/ rupture/ deform first before RV lifts
External Fire
RP 521 Figures • Heat up rate • Time to Rupture
Vessel under fire
will deform/ rupture before PSV lifts, as metal wall rapidly loses strength as its temperature rises. Blowdown Valves are provided to depressurize the vessel within 15 minutes Against fire: Blowdown FW spray Fireproofing
Temp °F
%
400
100
800
80
1,100
36
RVs do NOT protect against structural failure when the vessel is exposed to extremely high temperatures during a fire The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
1/3 Tensile
2/3 Yield
Max Temp
°C °F
This image cannot currently be display ed.
Pressure Surges Transient Analysis required for
Water hammer. 24 t piping flew off 800m. Sheared off telephone poles
water, liquid filled or rundown OSBL lines oil/condensate export pipelines
Transient Analysis is NOT required for ISBL piping. Short runs and generally do NOT have quick
closing valves
Code allowed - short term - margins may be used to avoid a PSV The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Design Tip: It is common for GRE Fire Water/ Sea Water piping to burst during start-up, fill the Flare KOD and bring the plant down. Have a good surge study; leave design and construction/start-up to a single source. Take exception from Owner, giving him the risk.
Seawater flooding a column sank semi-sub
Column Cases
Excess heat may not pressurize the exchanger but will over pressure the column
Reflux failure is usually the controlling case: Reflux Pump / Power Failure Reflux Control Valve Fails Closed Overhead Condenser Failure or Flooded on Draw-off Control Valve
Fails Closed Non-condensable Accumulates in the Condenser Operator Error: Block Valves Closed
Loss of Cold Feed Feed Control Valve Fails Closed or Feed Pump Fails - Transient Surge
in Vapour Rate
Excess Heat to Reboilers Steam or Heating Control Valve Fails Open Excessive Fuel to Fired Reboiler Safety Alerts Column blows off top – leakage reacts Additional Vapours generated Column overflows – 15 killed; 150 injured
Reboiler Tube Rupture
Credit: Reduced vaporization in reboiler at relieving pressure. Reduced ∆T relieving pressure reduces relief rate
Column Cases Column load calculations is complicated 3 approaches – flash, gross overhead vapour, unbalanced heat; last
one gives the best estimate
Column
Overhead Vapor, kg/h
DC Steam Stripper
Unbalanced Heat, kg/h
60,000
168,000
DC Fractionator
296,000
448,000
HC Debutanizer
69,000
171,000
Dynamic simulation can reduce
Dyn Sim load 60%. Case 2 PSV does not pop The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
column and reactor loads
DC Fractionator
Conventional, kg/h
Dyn Simulation, kg/h
.. Total power fail
448,000
259,000
.. Single power fail
85,000
0
258,000
172,000
.. Blocked outlet
From: “Optimize relief loads with dynamic simulation”, CL Xie, ZG Wang and YF Qin, HP, Dec 2013
Accidental Mixing of Fluids Runaway reaction - Polymerization: Some chemicals, when mixed in wrong
ratio or sequence may lead to run-away reaction Inadvertent mixing of reactive streams Decomposition or polymerization due to abnormal heat input or loss of cooling See Safety Alert
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Runaway Reaction Relief Rate Determination is complex. Inputs from
Owner, Catalyst Manufacturer, Process Licensor. Owner/ Licensor to provide the relief load. Pass them the responsibility
Bhopal. 4,000 to 10,000 dead; 500,000 injured
Liquid Overfill of Storage Tanks The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Inflow exceeds outflow Overfilling from an offsite
pump during start-up or LAH/LAHH failure The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Design Tip: 1. Let level transmitters for Control and Trip track each other. 2. While filling large tanks, let DCS put a time lock based on pumping rate and ullage
Vacuum Relief
This image cannot currently be display ed.
Equipment may come under vacuum: Fluid withdrawn without matching inflow Excessive condensation in Column
Overhead Condenser Condensation or cooling of vapours upon atmospheric temperature drop Compressor suction side blocked Condensing side of exchanger blocked in while cooling continues Draining with vent closed Cool down and condensing after steaming a vessel This image cannot currently be display ed.
This image cannot currently be display ed.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Vacuum Relief Equipment that could come under vacuum is designed to withstand full vacuum Note: For large diameter columns and storage tanks,
cost of designing to full vacuum is prohibitive
Check the consequences of air mixing with vessel inventory before providing vacuum relief. Usual to provide Nitrogen padding/ blanketing No RV required if Owner instructs that his administrative procedures can prevent vacuum Draining test water; Steam condensing after a steam-out
Atmospheric Tank Protection Inbreathing (vacuum relief) is required for Maximum outflow without matching inflow Vapour shrinkage due to atmosphere cooling –
showers etc Blanket gas supply valve fails/ closed
Out breathing (pressure relief) required for
Maximum inflow without matching outflow Vapour expansion due to atmosphere warming Blanket gas supply valve fails open Vapour outlet valve fails/ closed
Fire relief required unless tank has frangible
roof
Fire generally does not engulf the entire tank
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Atmospheric Tank Protection Refer API 2000, for calculation of relief load N2/ gas padding for thermal inbreathing/ outbreathing PVRV for thermal inbreathing/ outbreathing Gauge hatch / manway vents for fire relief Tanks have a low design pressure, mmWC. PVRV/
manway are weight loaded; sizing by vendor PVRVs installed directly on roof nozzle
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Blanket Gas Regulators
Emergency Vent Gauge Hatch and Manhole Cover
PVRV
Fired Heater Blocked outlet and thermal No PSV required for process coils, unless mandated
or underrated PSV required for BFW and Steam coils – Code/ IBR
Thermal PSV in Hot Oil WHRU Residual heat in refractory/ insulation. Not effective
against oil coking inside the tube
Pumps & Compressors Centrifugal Pump
Usually designed for shut-off or highest head at zero flow
Reciprocating/ Positive Displacement Pump/ Compressor
RV for blocked outlet. Due to pulsation in discharge pressure keep good margin between operating and set pressure
Centrifugal Compressor Suction side for settle-out pressure. 2-3 stages in a common casing may settle-out together + Check valve leak Refrigeration or low temp service ~ vapour pressure at ambient temperature Discharge/ Casing: Design for surge pressure at 105% speed with maximum [suction pressure; molecular weight] and minimum suction temperature [Oil & Gas Industry practice] or RV provided at 120% of Normal Operating Press Inter-stage: Usually fire case
When a compressor trips, discharge from other running compressors can back flow into the tripped one, pressurizing its Suction Drum
Typical Relief Cases – Oil & Gas
Flowline - Blocked Outlet/ Thermal Inlet Sep - Blocked Outlet LP Sep - Blocked Outlet/ Gas Blowby Compressor - Fire/ Check Valve Leakage Compressor Last Stage - Blocked Outlet ? Glycol Contactor – Fire Fuel Gas KOD - PCV Failure Glycol Pump - Blocked Outlet Filters - Fire Air Vessels - Fire
RVs may not be the right solution… For a few cases, RV is impractical. Instrumented safeguards is needed Hot Oil WHRU. Hot Oil Boiling Pt at Relief Press >≈ Incoming Flue Gas Temp Heat to boiling fluid ≈ zero Hot oil will decompose and coke before it boils Instrumented protection to remove source of heat + minimum flow at all times + thermal PSV against residual heat in WHRU
Export pipeline of 1,000 MMSCFD A huge flare. HIPPS contains the HP fluid avoiding a release Instrumented Protection to isolate the HP source such as compressor and/or HIPPS (2 independent SDV) from 2 “independent” trip systems.
READ ASME CODE CASE 2211-1, now part of RP 521, Annex E
Design Tip: SDVs leak, Ha Ha
Design Tip: HIPPS/ IPF requires Documented User Approval. Only User may specify pressure protection by system design.
SIZING
Design Tip: Analyzing Relief Scenarios and Estimating Relief Loads is the important part. Sizing is a matter of routine.
RV Sizing 3 Equations Vapour - Critical Steam - Critical (ASME Div VIII) Liquid K = Sizing constant W = Relief flow rate C = Coefficient P1 = Upstream relieving pressure Kd = Coefficient of discharge Kb /Kw = Back pressure correction factor Z = Compressibility M = Molecular weight T = Upstream relieving temperature A = Required orifice area
KW TZ A= CP1KdKb M KW A= P1KdKbKnKsh KQ G A= 38KdKwKv P1-P2
Kn = Correction factor for Napier Equation Ksh = Correction factor for steam superheat Kv = Correction factor for viscosity P2 = Total back pressure SG = Specific gravity of liquid Liquid sizing: trial & error step required. Start with an assumed size to determine Re and hence Kv. Repeat to match See API for sizing 2 Phase Flow. Older method of vapor + liquid area is no longer valid
RV Sizing Subcritical Flow – Vapour, pilot and conventional Valid for RVs that have their cold spring setting
adjusted to compensate for the constant superimposed BP Built-up back pressure 10% back pressure
RV Sizing Coefficient of Discharge Kd Depends on relief valve design National Boiler Board certifies capacities of all RVs Manufacturer back calculates Kd from certified capacity
and test conditions If unknown, assume 0.975 for vapour and 0.65 for liquid RV capacity must be checked based on vendor Kd For all vapour and liquid RVs, manufacturer should supply sizing calculation based on his Kd
Design Tip: Kd varies from manufacturer to manufacturer. Our calculations should not be passed to clients. Final calcs from supplier should be the deliverable.
RV Standard Sizes
Standard RV Sizes
API 526 Orifice Designation
RVs made in standard sizes Each standard orifice given a
letter designation Select a standard size larger than the calculated one If calculated size, marginally exceeds a standard size, it may be OK, as the actual orifice area for most RVs are higher than the standard API area. Actual areas are listed in National Boiler Board Book
Area, in2
Size D
0.110
E
0.196
F
0.307
G
0.503
H
0.785
J
1.287
K
1.838
L
2.853
M
3.600
N
4.340
P
6.380
Q
11.050
R
16.000
T
26.000
RV Standard Sizes
Standard RV Sizes
API 526 Orifice Designation
RV Inlet x Outlet Sizes
Area, in2
Size D
0.110
1 x2
E
0.196
1½ x 2
F
0.307
1½ x 3
G
0.503
H
0.785
J
1.287
K
1.838
L
2.853
6 x 10
M
3.600
8 x 10
N
4.340
P
6.380
Q
11.050
R
16.000
T
26.000
Size
2 x3 3 x4 3 x6 4 x6 6 x8
D
E
F
G
H
J
K
L
M
N
P
Q
R
T
Standard RV Sizes Air/Gas/Steam Service This image cannot currently be display ed.
API area is not actual RV area
Actual area and nozzle coefft vary from manufacturer to manufacturer
2J3 API Area = 1.287 in2
Actual area = 1.427 to 1.635 in2 Coeffts = 0.788 to 0.975
National Board certified capacity - based
on nozzle coefft and orifice area - varies Why the difference?
In 1962 ASME Sec VIII derated certified capacities by 10%. Manufacturers did not derate their advertised capacity or nozzle coefft, but increased nozzle area by 10%. But API orifice areas as advertised remain same.
Board RV Area is based on • Nozzle bore for full lift valves • Lift for restricted lift valve
KA is more comparable. Explanation AG/Crosby Advertised KA = 0.975*1.287 = 1.255 National Board = 0.788*1.635 = 1.288 API (K= 0.9) = 0.9*1.287 = 1.158 Actual capacity may be 10-16% more So don’t jump from P to R (73%) when calculated size marginally exceeds standard size
Thermal Expansion Relief Rate, q =
αv.φ K.d.c αv = cubic expansion coefft of liquid at expected temp φ = Heat Transfer Rate Exchangers: use max Heat Duty Solar Radiation: use as per Project Design Basis K = Sizing constant d = Relative Density c = Specific heat of trapped liquid
For thermal protection of piping, generally ¾” D 1” threaded
or 1” D 2” flanged RVs are provided; No calculations done
Fire Relief
Liquid:
Latent heat for multi-component is tricky, but rules of thumb help. λ = 50 to 100 units Assumed that entire heat goes to boil-off. With large liquid inventory, only a small part goes to vaporization; rest heats the liquid
Gas:
Temperature, T2, calculated under fire may exceed base equipment design temperature. RV with required inlet flange rating is usually not available. In RV data sheet, specify design temperature and indicate that T2 is for area calculation only. The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Fire Relief - Blowdown Without BDV, internal pressure (Hoop’s stress) rises over time;
Stress
metal’s ability to hold pressure (yield strength) falls with increasing temperature. The vessel will fail when internal stress exceeds ability Blowdown brings down internal pressure and stress. As long as internal stress is below allowable stress, vessel will not rupture Judiciously use to extend blowdown time when blowdown rate is higher than design inflow capacity to reduce flare size
Ka Boom
Time, minutes
API RP 521: Thinner plates (LP service)
heat up faster; higher the temperature, faster it ruptures If BDV initial pressure (PAHH/PSV) >> operating pressure, zoning can cut peak rate
Flow + Pressure
Fire Relief - Blowdown
RP 521 Figures • Heat up rate • Time to Rupture
Groups 1 +2 + 3
and adjacent equipment within a fire zone (8.6m radius x 7.6m high) are taken at BDV initial pressure; rest at operating pressure
Group 1, then Group 2 and last Group 3 50% reduction Flow
capacity
Pressure = Poe-θt Time
Take one source at a time. Loads from this
Staggered blowdown can reduce flare
Flow = Foe-θt
Time Staggered Blowdown • Each BDV with secured air vessel, sized for 3 valve strokes; PAL; 2 check valves at inlet; no bleeding devices like regulators
From: “Design staggered depressurization sequence for flare systems”, R Dole, S Bhatt and S Sridhar, HP, Dec 2013
INSTALLATION & ISOLATION
Design Tip: Improper installation restricts capacity. Next time you visit a plant, walk around and cringe in horror!!.
Inlet Line
Resonant Chatter in a pilot can self-destruct it
Size on RV rated flow - not on relief load Inlet loss 3% with pilots, use actual inlet pressure to size RV
Upstream of demister. from vapour space;
below Normal Liquid Level for PRV 10d min from Control Valve Free draining to source; Bleed/drain @inlet Nozzle Entrance Loss
Friction Loss
Entrance Loss 1 Velocity Head
Friction Loss
1 VH if RV is off vessel ½ VH if RV is off outlet pipe
RV mounted upright Inlet line/ Vessel Nozzle ≥ RV inlet
Bleed Hard T
Entrance Loss ½ Velocity Head
Design Tip: Common Error: Ignoring ∆P in common piping, specially in a group of vessels protected by a single RV.
Inlet 3% It is difficult to meet 3% From: “Address inlet pressure loss concerns with restricted lift relief devices”, Smith D, Yoram S, HP, Mar 2014
Outlet
Like high inlet loss, high back-pressure can make a RV chatter. As soon as RV closes, flow stops, back-pressure falls, making the RV to open
Atmospheric Discharge
Safe Location
To Safe Location - for steam, air and N2; not HC Weep or drain hole in outlet low point
To Closed Drain
¼“ drain hole
Thermal etc RV Avoid, if cross contamination is possible Avoid if water in drain will freeze
To Flare
Line should free drain to flare header; Top entry No liquid accumulation Backpressure limitation Outlet line size ≥ RV outlet < 70% sonic and ρV² criteria
Free Drain
Inlet/ Outlet Isolation
Inlet & outlet Isolation valves
If a spare RV is required by Owner,
install with FB inlet & outlet valves Inlet valve of one RV is LO and the other LC Some Owners require interlocked valve to ensure that one RV is always in service Why? Both outlet valves should be LO.
A (globe) vent valve across RV to depressurize before draining
Not permitted by ASME Section I; not recommended by ASME Section VIII If required by Owner, then both should be FB locked open (“LO” or “CSO”)
LO
LO 600 mm gap
LO LO LC
A 2nd ball isolation valve located 600mm upstream of vent valve in HP service, if globe valve is stuck on icing ~ JT cooling
A bleed valve u/s of RV inlet block valve ~ in-situ testing If Owner agrees, a single common LO outlet valve for all RVs in a system, say compressor train or Fuel Gas System
LO
Inlet & Outlet Piping Inlet Lead
Size, in Eq L, ft
Fittings No off
2
3
4
6
8
10
12
14
16
18
20
open system
25
25
25
25
25
25
25
25
25
25
25
Closed system
75
75
75
75
75
75
75
75
75
75
75
Eq L, ft each 3
Elbows
4
4
5
8
9
12
14
16
18
20
23
1
Hard T
10
14
19
28
37
47
55
62
72
82
90
1
Reducer
1
2
3
4
5
7
8
9
10
11
13
0
Gate Valve
2
2
3
4
6
7
9
10
11
12
14
Eq L, ft - Open system
48
53
62
81
94
115
130
144
161
178
197
Eq L, ft - Closed system
98
103
112
131
144
165
180
194
211
228
247
2
3
4
6
8
10
12
14
16
18
20
open system
25
25
25
25
25
25
25
25
25
25
25
Closed system
50
50
50
50
50
50
50
50
50
50
50
Outlet Lead
Size, in Eq L, ft
Fittings No off
Eq L, ft each 3
Elbows
4
4
5
8
9
12
14
16
18
20
23
1
Hard T
10
14
19
28
37
47
55
62
72
82
90
1
Reducer
1
2
3
4
5
7
8
9
10
11
13
0
Gate Valve
2
2
3
4
6
7
9
10
11
12
14
Eq L, ft - Open system
48
53
62
81
94
115
130
144
161
178
197
Eq L, ft - Closed system
73
78
87
106
119
140
155
169
186
203
222
Poor Piping
Design Tip: It is a pain; but MUST review RV inlet and outlet piping and pump suction piping in 3D model. Easier to do than “wish I could bury myself in sand” feeling at site
Pipers locate RVs at “convenient” locations – viz
access, ignoring inlet ∆P. Need to check piping 3D model Horizontal dead legs collect trash / liquid in service RVs in turbulent zone can chatter and get damaged Downstream of a Pressure Reduction Station – Fuel Gas? Downstream of orifice plates/ flow nozzles Downstream of pulsating compressor / pump discharge. Pilot
RVs may be better because of high seat loading This image cannot currently be display ed.
Ideal Piping The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Difficult to achieve but
recommended by suppliers This image cannot currently be display ed.
Common Errors
Prod Sep
Ignoring static head
LC
Hydrocyclone
Between upstream & downstream
equipment as in the case of Prod Sep and d/s vessel or Hydrocyclone Between PSV and piping at a lower deck
Pump at Upper Deck
Ignoring ∆P in common piping, specially in a group of vessels protected by a single RV Ignoring mechanical limit on backpressure. Bigger the RV lower is backpressure allowed.
Piping at Lower Deck
Friction Loss
150# RV Outlet Press Limit, psig at 100°F
Design Tip: Important to check mechanical limit on backpressure on flowing and non-flowing RVs. Forgotten by Process Engineers. See RP 526
Size
D–J
M
R
T
Convn
285
285
60
30
Bellow
230
80
60
30
PSV - 001
HIPPS Errors
HP | LP
PAHH PALL Riser SDV
PAHH PALL
HIPPS used
SDV-3 HP Section
SDV-1 SDV-2 HP | LP
Against PCV / choke failure Blocked outlet/ stuck pig/ hydrate blockage
Subsea Flowline
In subsea section to derate flowline/riser,
instead of designing for shut-in pressure Topside piping
LP Section
Subsea Wells
HP | LP Fortified Section
This image cannot currently be display ed.
Check Pressure build-up in trapped LP section by
the time PAHHs detect and fully closes SDVs Provide minimum length of fortified or HP section d/s of HIPPS SDVs - pig/ hydrate blockage, SDV leakage
Need to provide a PSV in LP SDVs leak!
This image cannot currently be display ed.
RV Discharge Velocity & Noise Force
Tail pipes may operate at high velocities Based on Process input, piping to calculate the reaction forces RV may need supports to counter momentum and velocity effects of the flowing fluid Dual outlet PSV can help mitigate – resultant force
Noise levels should be calculated per RP 520 Provide noise insulation or relocate RV away
Flow
Flow Induced Vibration Flow induced vibrations may result in fatigue
failure. May require piping supports, increased wall
thickness, etc The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
This image cannot currently be display ed.
This image cannot currently be display ed.
Failure to update Relief Studies Codes and standards; methods/ assumptions
keep changing … additional insights,, Flarenet RVs in old plants should be revisited every 10 years If control valves/ equipment have been replaced
In Oil & Gas plants, GORs, liquid profiles change
RELIEF SYSTEM DESIGN
Relief System Design Analyze Relief Scenarios
Analysis Calculate Relief Loads and RV Size for each Scenario to get Governing Case Sizing Summarize results for each RV for each contingency to determine Peak Load to Flare Info Required 1. Heat and Material Balance 2. Process Flow Diagrams (PFDs) 3. Piping and Instrumentation Drawings (P&IDs) 4. Instrument Data (Control Valve, Bypass, RO sizes, etc.) 5. Mechanical and Rotating Equipment Data
Total Load Reduction via Dyn Sim On total plant failure cases, viz Power, Cooling Water, Air, it is unlikely all the PSVs will pop at the same instant + maintain initial rate Columns may take time build to relief pressure Dynamic simulation can help find realistic load Note: Compressor interstage drum pops in total system
study but does not impact total load
Total Power Failure Fractionator
Conventional, kg/h
Dyn Sim - Individual, kg/h
Dyn Sim – System, kg/h
448,000
259,000
140,000
0
0
160,000
Stripper Feed Drum
45,000
45,000
50,000
Debutanizer
72,000
72,000
5,000
565,000
376,000
355,000
Comp Interstage Drum
Total
From: “Optimize relief loads with dynamic simulation”, CL Xie, ZG Wang and YF Qin, HP, Dec 2013
Total Load Reduction via Dyn Sim The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Dyn Sim total load is 275,000. But design taken as 355,000 kg/h
Total Power Failure Fractionator
Conventional, kg/h
Dyn Sim - Individual, kg/h
Dyn Sim – System, kg/h
448,000
259,000
140,000
0
0
160,000
Stripper Feed Drum
45,000
45,000
50,000
Debutanizer
72,000
72,000
5,000
565,000
376,000
355,000
Comp Interstage Drum
Total
From: “Optimize relief loads with dynamic simulation”, CL Xie, ZG Wang and YF Qin, HP, Dec 2013
Still Accidents Happen Boat hits platform The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
PSV not bolted right The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Boiler started without purging The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Hydrotest done with cold water The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Some of these accidents are not preventable by RVs but by • Common Sense • Good Operating Practice • Good Instrumentation & Controls
CS bend used instead of AS in H2 plant The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Piping Support Not Fire Proofed The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Bend d/s of water Injection or LCV = Erosion-corrosion The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Missing Check at UC The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Internal in Flare KOD The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Pig “Launched” The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
No gas detectors in onshore plant The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
Water Hammer The link ed image cannot be display ed. The file may hav e been mov ed, renamed, or deleted. Verify that the link points to the correct file and location.
THANK YOU