Man Machine Chart

Operation Description MAN MACHINE CHART Per shift 543 Takt Time in sec. 49 Walk Auto Customer Demand / month 380

Views 87 Downloads 3 File size 78KB

Report DMCA / Copyright

DOWNLOAD FILE

Recommend stories

Citation preview

Operation Description

MAN MACHINE CHART

Per shift

543

Takt Time in sec.

49

Walk Auto

Customer Demand / month

38000

Inspection Man

Work Element

Loading / Unloading

M/C

Inspection

Walk

8

20

2

2

2 4

6 8

10 12

14 16

18 20

22 24

26 28

30 32

34 36

38 40

42 44

46 48

50 52

54 56

58 60

62 64

66 68

70 72

74 76

78 80

82

Cycle time - 28 secs Scope for Improvement

4

18

2

6

6

16

Operator 1 : Manual time - 20 Secs Cycle time - 28 Secs Operator Idle time - 8 Secs Operator utilization - 71.42 %

Scope for Improvement

2

Cycle time - 22 secs 2

2 Scope for Improvement

Total Time (InSec)

4

8

24

68

Prepared by

Operator 2 : Manual Time - 16 Secs Cycle time - 22 Secs Operator Idle Time - 6 Secs Operator Utilization - 72.72 %

2

4

8

Accepted by

Approved by

84

86 88

90 92

94