FACTORY ACCEPTANCE TEST PROCEDURE GAS DETECTOR Sheet No : 3 of 11 A VISUAL CHECK AND DOCUMENTATION 1. Confirm and veri
Views 90 Downloads 1 File size 73KB
FACTORY ACCEPTANCE TEST PROCEDURE GAS DETECTOR
Sheet No : 3 of 11
A VISUAL CHECK AND DOCUMENTATION 1. Confirm and verify all document supported (such as certificate, etc) relate with equipment vendor supllied 2. Confirm and verify the quantity and specification of equipment vendor suplied is the same with order 3. Confirm and verify the installation accessories (such as mounting bracket, etc) is provide by vendor as per scope 4. Confirm and verify the tag number is provide by vendor as per scope
B FUNCTION TEST 1. 2. 3. 4. 5.
Unscrew the 4 off M6 screws (5.0mm A/F hexagon key) holding the cover assembly to the base. Lift the cover assembly away from the base of the enclosure to gain access to the interior. Cable termination must be follow standard wiring (reffered to Instruction Manual). Check power supply to detector, the supply voltage between 20-36 Vdc, nominal 24Vdc Take a sample of gas detector and doing test as bellow : a. Doing the ZERO GAS Test ( referred to Inspection and Test Procedure) b. Doing the SPAN GAS Test ( referred to Inspection and Test Procedure) 6. At the normal condition, purging the sensor with the gas calibration untill Alarm 1 and Alarm 2 indication shown 7. Check the output analog 4-20mA linear with gas concentration reading 8. Record the all activity according gas detector function test
Created by : Tech.Support - Arya Semesta
Revisi No : 0/2013
FACTORY ACCEPTANCE TEST PROCEDURE MANUAL ALARM CALLPOINT
Sheet No : 4 of 11
A VISUAL CHECK AND DOCUMENTATION 1. Confirm and verify all document supported (such as certificate, etc) relate with equipment vendor supllied. 2. Confirm and verify the quantity and specification of equipment vendor suplied is the same with order. 3. Confirm and verify the installation accessories (such as mounting bracket, etc) is provide by vendor as per scope. 4. Confirm and verify the tag number is provide by vendor as per scope.
B FUNCTION TEST 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
Unscrew the 4 off M6 screws (5.0mm A/F hexagon key) holding the cover assembly to the base. Lift the cover assembly away from the base of the enclosure to gain access to the interior. Cable termination must be follow standard wiring (reffered to Technical Manual). Lifted the spring loaded flap on the front of the unit, then pulling down the handle underneath. Connect cable from Pull Station Unit with Multimeter, and Multimeter display shown Short Circuit. For the reset the unit, first raise the lift flap away from the pull handle. Use the key (provide with the unit) release the pull handle which can be returned to its original position. Release the pull handle which can be returned to its original position. Connect cable from Pull Station Unit with Multimeter, and Multimeter display shown Open Circuit. Screwing back the 4 off M6 screws (5.0mm A/F hexagon key) holding the cover assembly to the base. Record the all activity according Pull Station function test
Created by : Tech.Support - Arya Semesta
Revisi No : 0/2013
FACTORY ACCEPTANCE TEST PROCEDURE SOUNDER - BEACON
Sheet No : 5 of 11
A VISUAL CHECK AND DOCUMENTATION 1. Confirm and verify all document supported (such as certificate, etc) relate with equipment vendor supllied 2. Confirm and verify the quantity and specification of equipment vendor suplied is the same with order 3. Confirm and verify the installation accessories (such as mounting bracket, etc) is provide by vendor as per scope 4. Confirm and verify the tag number is provide by vendor as per scope.
B FUNCTION TEST SOUNDER 1. 2. 3. 4. 5.
Unscrew and remove the 4 off M6 screws (5.0mm A/F hexagon key) holding the cover assembly to the base. Lift the cover assembly away from the base of the enclosure to gain access to the interior. Cable termination should be in accordance with specifications applying to the required application Check power supply to detector, the supply voltage between 18-32 Vdc, nominal 24Vdc. Use a 5-way DIL switch selects the tone required. The settings for the standard tones are shown in table (reffered to Technical Manual) BEACON
1. 2. 3. 4. 5.
Unscrew and remove the 6 off M8 screws (6.0mm hexagon key) holding the cover assembly to the base. Lift the cover assembly away from the base of the enclosure to gain access to the interior. Cable termination should be in accordance with specifications applying to the required application The operating voltage of the unit is stated on the unit label. The unit can be powered directly only Record the all activity according Sounder-Beacon function test
Created by : Tech.Support - Arya Semesta
Revisi No : 0/2013
FACTORY ACCEPTANCE TEST PROCEDURE LNG SPILL DETECTOR
Sheet No : 6 of 11
A VISUAL CHECK AND DOCUMENTATION 1. Confirm and verify all document supported (such as certificate, etc) relate with equipment vendor supllied. 2. Confirm and verify the quantity and specification of equipment vendor suplied is the same with order. 3. Confirm and verify the installation accessories (such as mounting bracket, etc) is provide by vendor as per scope. 4. Confirm and verify the tag number is provide by vendor as per scope.
B FUNCTION TEST 1. 2. 3. 4. 5. 6.
An external power supply is required to operate the transmitter. Remove the terminal block cover (if applicable). Cable termination must be follow standard wiring (reffered to Instruction Manual). Check power supply to detector, the supply voltage between 12-42Vdc, nominal 24Vdc. From the home screen display, select Loop Test menu and choose Analog Output Connect an external ampere meter in series with the transmitter loop (so the power to the transmitter goes goes through the meter at some point in the loop.) 7. In the test loop, check that the transmitter’s actual mA output and the HART mA reading are the same value. If the readings do not match, either the transmitter requires an output trim or the current meter is malfunction. 8. After completing the test, the display returns to the loop test screen and allows the user to choose End menu. 9. Record the all activity according gas detector function test.
Created by : Tech.Support - Arya Semesta
Revisi No : 0/2013
FACTORY ACCEPTANCE TEST Visual Inspection Report No
A
B
C
D
Description Documentation * Cert. of Conformance * Cert. of Origin * Hazardous Certificate * Calibration Certificate * Etc Specification * Refer to Datasheet * Refer to Requirement Test & Comm. Tools * Portable Purge Calib. * Gas Cylinder CH4 * Ultima XP Calibrator Installation Accessories * SS Tag Number * SS U Bolt c/w. Nuts * SS Mounting Plate
Completed Yes No
Item
Sheet No : 7 of 11 Quantity
Comment
All Item Supplied
All Item Supplied
Gas Detector
All Item Supplied
NOTE :
ACCEPTANCE FORM Checked & Inspected PT. MSA Indonesia PT. Tracon Industri PT. Rekayasa Industri
Name
Signature
Date
FACTORY ACCEPTANCE TEST Function Test Report - Gas Detector No.
Item To Be Tested
Analog Output Action Result
Comment
Sheet No : 8 of 11
Zero - Span Display Result
Comment
Remark
A ZERO - SPAN 1
Zero Gas (Using Air)
0%LEL
2
Span Gas ( 50%LEL CH4)
50%LEL
3
Normal Condition
0%LEL
B ANALOG OUTPUT 4 5 6
Force Analog Output (4mA - 0%LEL) Force Analog Output (12mA - 50%LEL) Force Analog Output (20mA - 100%LEL)
4mA at DVM 12mA at DVM 20mA at DVM
C GAS TEST READING 1
Low Alarm (Alarm 1)
2
High Alarm (Alarm 2)
3
Fault Alarm
NOTE :
ACCEPTANCE FORM Checked & Inspected PT. MSA Indonesia PT. Tracon Industri PT. Rekayasa Industri
Name
Signature
Date
FACTORY ACCEPTANCE TEST Function Test Report - LNG Spill Detector No.
Item To Be Tested
Electrical Action Result
Comment
Sheet No : 9 of 11
Analog Output Action Result
Comment
Remark
A ELECTRICAL 1
Cable Termination
2
Power Supply (12 - 42Vdc)
Refer to Manual 24Vdc at DVM
B ANALOG OUTPUT 4 5 6
Force Analog Output (4mA - 0%FS) Force Analog Output (12mA - 50%FS) Force Analog Output (20mA - 100%FS)
4mA at HartCom 12mA at HartCom 20mA at HartCom
C TEMP. TEST READING 1
Low Alarm (Alarm 1)
2
High Alarm (Alarm 2)
3
Fault Alarm
NOTE :
ACCEPTANCE FORM Checked & Inspected PT. MSA Indonesia PT. Tracon Industri PT. Rekayasa Industri
Name
Signature
Date
FACTORY ACCEPTANCE TEST Function Test Report - Sounder Beacon No.
Item To Be Tested
Mechanical Action Result
Comment
Sheet No : 10 of 11
Electrical Action Result
Comment
Remark
A SOUNDER 1
Cable Termination
2
Power Supply (18-32Vdc)
3 4
Refer to Manual 24Vdc at DVM Tone Alarm 1 Tone Alarm 2
5 Way DIL Switch Select Tones for Alarm 1 5 Way DIL Switch Select Tones for Alarm 2
B BEACON 1
Cable Termination
2
Power Supply
3
Beacon Type - Red
4
Beacon Type - Amber
Refer to Manual Refer to Label Unit Red Amber
NOTE :
ACCEPTANCE FORM Checked & Inspected PT. MSA Indonesia PT. Tracon Industri PT. Rekayasa Industri
Name
Signature
Date
FACTORY ACCEPTANCE TEST Function Test Report - Manual Alarm CallPoint No.
Item To Be Tested
Mechanical Action Result
Comment
Sheet No : 11 of 11
Electrical Action Result
Comment
Remark
A MECHANICAL 1
Spring Loaded Flap
Lifted
2
Pull Handle
Pulled Down
3
Special Key
Turned
B ELECTRICAL 1 2
Lifted Spring Loaded Flap and Pulled Down Handle Use Special Key and Release Pull Handle
SC at DVM OC at DVM
NOTE :
ACCEPTANCE FORM Checked & Inspected PT. MSA Indonesia PT. Tracon Industri PT. Rekayasa Industri
Name
Signature
Date