Bill

PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III INSTALLATION CHECK LIST FOR HVAC CONTROL PANEL REV.

DRAWING NO.

LOCATION

SYSTEM DESCRIPTION

Sr. No.

Description

Yes

1

Check the panel against approved submittal.

2

Confirm the size, location, orientation of panel for easy accessibility for operation/maintenance.

3

Confirm the mounting arrangements against manufacturer’s recommendation.

4

Check that proper, neat and clean/clear entry of cables/wires is available.

5

Check all wiring and internal installation are mounted and labeled correctly

6

Check all cable glands secure earth rings fitted, bonded to the Main Earthing Conductor.

7

All Cables are identified.

8

Panel identification labels fixed.

9

All neutral and earth cables identified to correspond with appropriate live conductor.

10

All Fuses, MCBs, MCCBs are of correct rating and type and are properly identified.

No

Remarks

DOCUMENT NUMBER

ISSUE

PAGE NO.

DATE

BILT/J-225/QAP/AC-08

REV. 0

1 of 2

16-09-2009

Bill

PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III INSTALLATION CHECK LIST FOR HVAC CONTROL PANEL REV.

DRAWING NO.

LOCATION

SYSTEM DESCRIPTION

11

12

All cable termination, terminal lugs are proper type and secure with identification Check earthing of panel.

Sr. No. 13

Description

Yes

No

Remarks

Check wiring to DDC controller.

CONSULTANTS COMMENTS:

ENGINEER/SUPERVISOR (BILT)

NAME

SIGN.

QA / QC ENGINEER (BILT)

NAME

SIGN.

CONSULTANT/CLIENT

NAME

SIGN

DOCUMENT NUMBER

ISSUE

PAGE NO.

DATE

BILT/J-225/QAP/AC-08

REV. 0

1 of 2

16-09-2009