PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III INSTALLATION CHECK LIST FOR HVAC CONTROL PANEL REV.
DRAWING NO.
LOCATION
SYSTEM DESCRIPTION
Sr. No.
Description
Yes
1
Check the panel against approved submittal.
2
Confirm the size, location, orientation of panel for easy accessibility for operation/maintenance.
3
Confirm the mounting arrangements against manufacturer’s recommendation.
4
Check that proper, neat and clean/clear entry of cables/wires is available.
5
Check all wiring and internal installation are mounted and labeled correctly
6
Check all cable glands secure earth rings fitted, bonded to the Main Earthing Conductor.
7
All Cables are identified.
8
Panel identification labels fixed.
9
All neutral and earth cables identified to correspond with appropriate live conductor.
10
All Fuses, MCBs, MCCBs are of correct rating and type and are properly identified.
No
Remarks
DOCUMENT NUMBER
ISSUE
PAGE NO.
DATE
BILT/J-225/QAP/AC-08
REV. 0
1 of 2
16-09-2009
Bill
PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III INSTALLATION CHECK LIST FOR HVAC CONTROL PANEL REV.
DRAWING NO.
LOCATION
SYSTEM DESCRIPTION
11
12
All cable termination, terminal lugs are proper type and secure with identification Check earthing of panel.
Sr. No. 13
Description
Yes
No
Remarks
Check wiring to DDC controller.
CONSULTANTS COMMENTS:
ENGINEER/SUPERVISOR (BILT)
NAME
SIGN.
QA / QC ENGINEER (BILT)
NAME
SIGN.
CONSULTANT/CLIENT
NAME
SIGN
DOCUMENT NUMBER
ISSUE
PAGE NO.
DATE
BILT/J-225/QAP/AC-08
REV. 0
1 of 2
16-09-2009