TRABAJO ENCARGADO DE LA CONSTRUCTORA “EL DUQUE S.A.” PRESENTADO POR: INTEGRANTES: CCAMA LIPA JHON NILTON CCOPA PERALTA WILLIAM JOSUE LLANOS CANLLAHUI GELIN RINA MILLONES RODRIGUEZ RAUL CARLOS EDUARDO PACHECO RAMOS ENRIQUE TRAMO DE EJECUCION – CONSTRUCTORA “EL DUQUE” 𝑇𝑅𝐴𝑀𝑂 𝑋 – 𝑌 = 101 𝐾𝑀 𝑃𝐿𝐴𝑁𝑇𝐴 𝐷𝐸 𝐴𝑆𝐹𝐴𝐿𝑇𝑂 = 00 + 40 𝐾𝑀 (𝐷𝐸𝑁𝑇𝑅𝑂 𝐷𝐸 𝑋 − 𝑌) MATERIAL PARA PRODUCIR ASFALTO 𝐴𝑅𝐸𝑁𝐴 𝐹𝐼𝑁𝐴 (𝐶𝐴𝑁𝑇𝐸𝑅𝐴 𝐶𝐴𝐿𝐴𝑀𝐴𝑅) = 00 + 90 𝐾𝑀 (𝐷𝐸𝑁𝑇𝑅𝑂 𝐷𝐸 𝑋 − 𝑌) 𝑃𝐼𝐸𝐷𝑅𝐴 𝐶𝐻𝐴𝑁𝐶𝐴𝐷𝐴 (𝐶𝐴𝑁𝑇𝐸𝑅𝐴 𝐼𝐺𝑈𝐴𝑁𝐴) = 00 + 05 𝐾𝑀(𝐷𝐸𝑁𝑇𝑅𝑂 𝐷𝐸 𝑋 − 𝑌) 𝐿𝐼𝑄𝑈𝐼𝐷𝑂 𝐴𝑆𝐹𝐴𝐿𝑇𝐼𝐶𝑂 ( 𝑃𝐸𝑇𝑅𝑂𝐿𝐸𝑂𝑆 𝑃𝐸𝑅𝑈 𝑇𝐴𝐿𝐴𝑅𝐴) = 60𝐾𝑀 𝐴𝐿 𝑆𝑈𝑅 𝐷𝐸 𝐼𝑁𝐹𝐼𝐸𝑅𝑁𝐼𝐿𝐿𝑂 𝑃𝐸𝑇𝑅𝑂𝐿𝐸𝑂 (𝑇𝐴𝐿𝐴𝑅𝐴) ( 𝑃𝐸𝑇𝑅𝑂𝐿𝐸𝑂𝑆 𝑃𝐸𝑅𝑈 𝑇𝐴𝐿𝐴𝑅𝐴) = 60𝐾𝑀 𝐴𝐿 𝑆𝑈𝑅 𝐷𝐸 𝐼𝑁𝐹𝐼𝐸𝑅𝑁𝐼𝐿𝐿𝑂 AGUA PARA LA REFRIGERACION: 𝐴𝐺𝑈𝐴 (𝑄𝑈𝐸𝐵𝑅𝐴𝐷𝐴 𝐿𝑂𝑆 𝐵𝑅𝑈𝐽𝑂𝑆) = 10𝐾𝑀 (𝐷𝐸𝑁𝑇𝑅𝑂 𝐷𝐸 𝑋 − 𝑌) FUNCIONAMIENTO DE LA PLANTA: 𝐴𝐺𝑈𝐴 𝑌 𝑃𝐸𝑇𝑅𝑂𝐿𝐸𝑂 PRODUCCION: 𝐶𝐴𝑃𝐴𝐶𝐼𝐷𝐴𝐷 𝐷𝐸 𝑃𝑅𝑂𝐷𝑈𝐶𝐶𝐼𝑂𝑁 = 180 𝑚3/ℎ 𝐻𝑂𝑅𝐴𝑆 𝐸𝐹𝐸𝐶𝑇𝐼𝑉𝐴𝑆 𝐷𝐸 𝑇𝑅𝐴𝐵𝐴𝐽𝑂 − 𝑃𝐿𝐴𝑁𝑇𝐴 𝐷𝐸 𝐴𝑆𝐹𝐴𝐿𝑇𝑂 = 6 𝐻𝑂𝑅𝐴𝑆 𝑃𝑅𝑂𝐷𝑈𝐶𝐶𝐼𝑂𝑁 𝐷𝐼𝐴𝑅𝐼𝐴 = 1080 𝑚3 𝑃𝑅𝑂𝐷𝑈𝐶𝐶𝐼𝑂𝑁 𝐷𝐸 10 𝐷𝐼𝐴𝑆 = 10𝐷𝐼𝐴𝑆 ∗ 6𝐻/𝐷𝐼𝐴 ∗ 180𝑚3/𝐻 = 10800 SOLICITUD DEL ALCALDE DE INFIERNILLO: 𝑃𝑅𝐸𝑆𝑈𝑃𝑈𝐸𝑆𝑇𝑂 (𝐷𝐸𝑆𝑃𝑈𝐸𝑆 𝐷𝐸 10 𝐷𝐼𝐴𝑆 𝐷𝐸 𝐷𝐸𝐿 𝐼𝑁𝐼𝐶𝐼𝑂) =? ? ? ? ? ? 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 12960 𝑚3 RESIDENTE DE LA COMPAÑÍA V Y L CONTRATISTAS GENERALES S.A TRAMO Y – Z: 𝑆𝑂𝐿𝐼𝐶𝐼𝑇𝐴 𝐴𝑆𝐹𝐴𝐿𝑇𝑂 𝐷𝑈𝑅𝐴𝑁𝑇𝐸 20 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 = 95𝐾𝑀 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 900 𝑚3/𝑑𝑖𝑎 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 𝐴 20 𝐷𝐼𝐴𝑆 = 18000 𝑚3 SR. GERMAN MACHACA DRILLING PERFORACIONES S.A. :

𝐶𝑈𝐴𝑅𝑇𝐸𝐿 (𝑂𝐸𝑆𝑇𝐸 𝐷𝐸 𝐼𝑁𝐼𝐹𝐸𝑅𝑁𝐼𝐿𝐿𝑂) 𝐴 5 𝐾𝑀, 𝑆𝑂𝐿𝐼𝐶𝐼𝑇𝐴 𝑃𝑅𝐸𝑆𝑈𝑃𝑈𝐸𝑆𝑇𝑂 = ? ? ? ? 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 8640 𝑚3 EL DUQUE CUENTA CON: 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 = 20 𝑈𝑁𝐼𝐷𝐴𝐷𝐸𝑆 𝐷𝐸 (15 𝑚3) 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 = 35 𝑈𝑁𝐼𝐷𝐴𝐷𝐸𝑆 𝐷𝐸 (10 𝑚3) 𝐶𝐴𝑀𝐼𝑂𝑁𝐸𝑆 𝐶𝐼𝑆𝑇𝐸𝑅𝑁𝐴 = 3 𝑈𝑁𝐼𝐷𝐴𝐷𝐸𝑆 𝐷𝐸 (8000 𝐺𝐴𝐿𝑂𝑁𝐸𝑆) = 30.28 𝑚3   

𝐶𝐴𝑀𝐼𝑂𝑁 𝐴𝐺𝑈𝐴 = 30.28 𝑚3 (8000 𝐺𝐴𝐿𝑂𝑁𝐸𝑆) 𝐶𝐴𝑀𝐼𝑂𝑁 𝑃𝐸𝑇𝑅𝑂𝐿𝐸𝑂 = 30.28 𝑚3 (8000 𝐺𝐴𝐿𝑂𝑁𝐸𝑆) 𝐶𝐴𝑀𝐼𝑂𝑁 𝐿𝐼𝑄𝑈𝐼𝐷𝑂 𝐴𝑆𝐹𝐴𝐿𝑇𝐼𝐶𝑂 = 30.28 𝑚3 (8000 𝐺𝐴𝐿𝑂𝑁𝐸𝑆)

FORMAS DE USO DEL DUQUE PARA: 𝑀𝐸𝑍𝐶𝐿𝐴 𝐴𝑆𝐹𝐴𝐿𝑇𝐼𝐶𝐴 = 15 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 𝐷𝐸 (15 𝑚3), (𝐻𝐴𝐿𝐿𝐴𝑅 𝐶𝑈𝐴𝑁𝑇𝑂𝑆 𝑉𝐼𝐴𝐽𝐸𝑆 𝐻𝐴𝐶𝐸 𝐶𝐴𝐷𝐴 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸 𝐴𝐿 𝐷𝐼𝐴) 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 𝑉𝑂𝐿𝐴𝑁𝑇𝐸𝑆 = 5 (15 𝑚3) 𝐴𝑅𝐸𝑁𝐴 𝐺𝑅𝑈𝐸𝑆𝐴(𝐹𝐼𝑁𝐴) = 20 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 𝐷𝐸 (10 𝑚3) 𝑃𝐼𝐸𝐷𝑅𝐴 𝐶𝐻𝐴𝑁𝐶𝐴𝐷𝐴 = 15 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 (10 𝑚3) CALCULO DE VOLUMEN DE ASFALTO TRAMO X-Y “CONSTRUCTORA EL DUQUE”: 𝐸𝑆𝑃𝐸𝑆𝑂𝑅 = 2 𝑃𝑈𝐿𝐺 = 0.0254 𝑚 𝐴𝑁𝐶𝐻𝑂 𝐷𝐸 𝑉𝐼𝐴 = 9.2 𝑚 𝐿𝑂𝑁𝐺𝐼𝑇𝑈𝐷 = 101 𝐾𝑀 = 101000 𝑚 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 𝑇𝑅𝐴𝑀𝑂 𝑋 − 𝑌 = 23601.68 𝑚3 𝑃𝑅𝑂𝐷𝑈𝐶𝐶𝐼𝑂𝑁 𝐷𝐼𝐴𝑅𝐼𝐴 = 1080 𝑚3/𝑑𝑖𝑎 CALCULO DE DIAS TRAMO X-Y “CONSTRUCTORA EL DUQUE”: 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 23601.68 𝑚3 = (23601.68 𝑚3)/(1080 𝑚3/𝑑𝑖𝑎) 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 23601.68 𝑚3 = 21.85 𝐷𝐼𝐴𝑆 = 22 𝐷𝐼𝐴𝑆 CALCULO DE DIAS ALCALDE DE INFIERNILLO: 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 12960 𝑚3 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 12960 𝑚3 = (12960 𝑚3)/(1080 𝑚3/𝑑𝑖𝑎) 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 23601.68 𝑚3 = 21.85 𝐷𝐼𝐴𝑆 = 12 𝐷𝐼𝐴𝑆 CALCULO DE DIAS COMPAÑÍA V Y L CONTRATISTAS GENERALES S.A TRAMO Y – Z: 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 900 𝑚3/𝑑𝑖𝑎 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 𝐴 20 𝐷𝐼𝐴𝑆 = 18000 𝑚3 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 18000 𝑚3 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 18000 𝑚3 = (18000 𝑚3)/(1080 𝑚3/𝑑𝑖𝑎)

𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 23601.68 𝑚3 = 16.67𝐷𝐼𝐴𝑆 = 17 𝐷𝐼𝐴𝑆 CALCULO DE DIAS SR. GERMAN MACHACA DRILLING PERFORACIONES S.A. : 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 8640 𝑚3 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 8640 𝑚3 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 8640 𝑚3 = (8640 𝑚3)/(1080 𝑚3/𝑑𝑖𝑎) 𝐷𝐼𝐴𝑆 𝑃𝐴𝑅𝐴 𝐶𝑈𝑀𝑃𝐿𝐼𝑅 𝑀𝐸𝑇𝐴 𝐷𝐸 23601.68 𝑚3 = 8 𝐷𝐼𝐴𝑆 = 8 𝐷𝐼𝐴𝑆 TIEMPO DE DURACION DEL ASFALTADO: 62 𝐷𝐼𝐴𝑆 𝑈𝑇𝐼𝐿𝐸𝑆 ATENCION DE CAMIONES CISTERNA 2 VECES POR SEMANA (HORA 5 PM) TOTAL DE DIAS QUE SE REQUERIRIA PARA ATENDER A TODOS 𝑫𝑰𝑨𝑺 = 𝟐𝟐 + 𝟏𝟐 + 𝟏𝟕 + 𝟖 𝑫𝑰𝑨𝑺 = 𝟓𝟗 𝑫𝑰𝑨𝑺 PRODUCCION DIARIA : 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 𝐷𝐼𝐴𝑅𝐼𝑂 = 1080 𝑚3 PARA LA MEZCLA ASFALTICA SE TIENE: 𝑀𝐸𝑍𝐶𝐿𝐴 𝐴𝑆𝐹𝐴𝐿𝑇𝐼𝐶𝐴 = 15 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 𝐷𝐸 (15 𝑚3), VOLUMEN DE DESPACHADO EN UN VIAJE (15 VOLQUETES)=15*15=225 m3 PAR QUE TODO EL VOLUMEN SE ACABE TODOS LOS VOLQUETES DEBERIAN HACER:   



12 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 5 𝑉𝐼𝐴𝐽𝐸𝑆 = 12 ∗ 15 ∗ 5 = 900 𝑚3 3 𝑉𝑂𝐿𝑄𝑈𝐸𝑇𝐸𝑆 4 𝑉𝐼𝐴𝐽𝐸𝑆 = 3 ∗ 15 ∗ 4 = 180 𝑚3 𝑉𝑂𝐿𝑈𝑀𝐸𝑁 = 900 + 180 = 1080 𝑚3 (𝐷𝐼𝐴𝑅𝐼𝑂𝑆)

CÁLCULOS DESARROLLADOS EN EXCEL

CONCLUSIONES:







 

Según el cronograma de obra solo se dispondrán de 10 días para que la obra tenga libre antes de poder abandonar el lugar donde se encuentra el campamento para lo cual, si se abastece a otras entidades produciría que exista una ampliación el en el cronograma de avance, lo cual no es factible debido a que el alquiler no puede extenderse. En el caso de querer abastecer seria factible ayudar al alcalde, pero hacer un traslado de la planta cerca a la zona de construcción de las avenidas para que el abastecimiento sea rápido y al mismo tiempo ayudar solo con el abastecimiento al SR. GERMAN MACHACA en el caso que aún requiera los servicios de la planta asfaltadora. Se podría reprogramar el cronograma de obra para abastecer a los 3 necesitados, pero para ello tendría que haber una programación y pago para abastecer más días con el alquiler de la zona donde se encuentra el campamento. En el caso de los volquetes volantes se necesita abastecerlos para el transporte de agua en cisternas debido a que el agua para abastecimiento de la planta es muy poco. Debido a que no se puede realizar alquiler de cisterna se podría realizar extracción del mismo río por medio de motor sumergible y manguera.