Connecting LMP cable for commissioning UltraSite EDGE BTS 1 de 2 http://127.0.0.1:43231/NED/NED?service=printview&libr
Views 84 Downloads 5 File size 84KB
Connecting LMP cable for commissioning UltraSite EDGE BTS
1 de 2
http://127.0.0.1:43231/NED/NED?service=printview&library=usebts_...
Nokia UltraSite EDGE BTS, Library: Release 6, Product Documentation Identifier: dn03332997-1-en
Connecting LMP cable for commissioning UltraSite EDGE BTS Before you start Review the Overview of commissioning UltraSite EDGE BTS. Pay careful attention to all Warnings and Cautions.
Summary The LMP cable connects the PC running BTS Manager SW to the BOI unit in the BTS.
Figure: LMP cable Table: LMP cable connector pin order BTS end, D9 male, pin number PC end, D9 female, pin number PC end, D25 female, pin number 2, LMP in
3, transmitted data
2, transmitted data
3, LMP out
2, received data
3, received data
5, ground
5, ground
7, ground
Steps 1. Remove the protective cover from the LMP port on the BOIx for GSM/EDGE connection. Alternatively, remove the protective cover from the BTS master WAM unit for WCDMA connection.
03/03/2010 8:45
Connecting LMP cable for commissioning UltraSite EDGE BTS
2 de 2
http://127.0.0.1:43231/NED/NED?service=printview&library=usebts_...
2. Connect the D9 female connector to the PC. 3. Connect the D9 male connector to the LMP port on the BOIx for GSM/EDGE connection. Alternatively, connect the D25 female connector to the BTS master WAM unit for WCDMA connection. Printed from NED6 Copyright © Nokia Siemens Networks. All rights reserved.
03/03/2010 8:45