“FUNDAMENTALS OF LEAN CONSTRUCTION” LEAN” Luai M. El-Sabek, Ph.D., PE, PEng, PMP , CM-Lean Operations Director Lean Con
Views 94 Downloads 3 File size 5MB
“FUNDAMENTALS OF LEAN CONSTRUCTION” LEAN” Luai M. El-Sabek, Ph.D., PE, PEng, PMP , CM-Lean Operations Director
Lean Construction Institute – Qatar
January 25, 2020
INSPIRING QUOTE
2
OBJECTIVES Status of construction industry – identify the gap Overcome stereotypes: “manufacturing” “this is what we do” ”there nothing new” Establish general awareness of Lean Construction: What? Why? How? Create an incentive to initiate / continue a Lean journey in your project(s) or organization Establish a demand for Lean education Status of Lean Construction implementation in Qatar Lean Construction Institute - Qatar
3
THE PROBLEM – 1) POOR PRODUCTIVITY
Productivity by industry in the US ( indexed; 1.0 = 1950)
4
THE PROBLEM – 2) WASTE Manufacturing
Construction
57%
12%
Construction Industry Institute, 2004
5
THE PROBLEM – 3) INEFFICIENCY
McGraw Hill 2013
6
THE PROBLEM WITH CONSTRUCTION TODAY… Injuries are too high. Rework and wastes are high. Construction productivity is declining. Construction costs are skyrocketing Profit margins are shrinking.
7
THE SOLUTION – DIFFERENT THINKING (Breakthrough Learning)
Observer
Action
Outcomes
Different Outcome => Change Action (Incremental Learning) 8
THE SOLUTION – PRODUCTION THEORY
(Koskela 1992)
9
DOES IT WORK?
Toyota Production System (TPS) 1950s (Taiichi Ohno) Construction Vs. Manufacturing
Project Vs. Production
Construction projects are unique and have distinctive peculiarities i.e. on site production, one-of-a-kind production, and temporary (Koskela, 2000). IGLC: construction is fundamentally different from manufacturing. Therefore, reinterpretation of the theory of is needed to develop a theory-based methodology for construction. Lean + Construction = creativity
10
WHAT IS LEAN CONSTRUCTION?
Creating ideal state of designing and constructing a facility using standard processes to: Provide / generate value Eliminate waste Continuously improve
11
WHAT IS NOT LEAN CONSTRUCTION? Lean
Production grafted onto construction Cost Cutting Eliminating Jobs Beating up suppliers and subcontractors Doing Value Engineering During Construction Being Stingy
12
LEAN CONSTRUCTION
Lean Construction Institute (LCI)
“Lean Construction is a production management-based approach to project delivery – a new way to design and build capital facilities to maximize value and minimize waste….”
AGC OF America
“Lean Construction is a set of ideas, practiced by individuals in the construction industry, based in the holistic pursuit of continuous improvements aimed at minimizing costs and maximizing value to clients in all dimensions of the built and natural environment: planning, design, construction, activation, operations, maintenance, salvaging, and recycling.” 13
VALUE
Value is generated when: Customer
capabilities are expanded, covering new needs and purposes.
The
facility better fulfills the purposes and demands of customers, operators, and other stakeholders
However, value is not just fitness for use or performance relative to cost
(LCI 2002)
14
CUSTOMER / PROVIDER RELATION Purpose!!
Customer/Client/Stud ent/Citizen Cost Quality Availability Experience
Value Promise !!!
Organization/Company
Profit Business Growth Reputation
15
VALUE PROMISE DELIVERY BASICS
A process is a sequence of actions that must be executed correctly in the right time and order to create value for a customer – or simply a way of getting things done.
Customer Order Process Product Shipment/ Service fulfillment 16
VALUE PROMISE DELIVERY BASICS
Customer Order Waste
Value = Results – Expectations
Process
Waste
Product Shipment/ Service fulfillment 17
LEAN THINKING
18
WASTE Wastes
Examples of Wastes in Construction
Ohno (1988)
ElSabek and McCabe 2018) Excess Materials of concrete or asphalt Over excavation Raw materials on site work in progress Scope elegance
3) Over-processing
4) Defects
Non-conformance to quality
5) Unnecessary motion
Movement at site
6) Unnecessary transport
Transportation of workers to/from labour camp to field and to/from break area Mob / demob of materials Worker waiting for work or work waiting for workers Idle equipment
1) Overproduction 2) Inventories
7) Waiting
19
TRADITIONAL CONSTRUCTION MANAGEMENT
(Howell 2010)
20
INTEGRATED PROJECT DELIVERY
(Howell 2010)
21
EXAMPLES OF ENABLING TOOLS
Integrated Project Delivery (IPD) ® ® Last Planner System (LPS ) IMPact Framework Lean Design (Target Value Design, Process Design, BIM, and VDC) Root cause analysis (5 Why and fishbone) Problem Solving Techniques (A3s) Decision Making System (Choosing By Advantages) Continuous improvement (PDCA, Kaizen, Plus/Delta) Error Proofing 5S Plus Safety - Lean Assembly (Sort, Set, Shine, Standardize, & Sustain) Offsite fabrication Just in Time (JIT) Value Stream Mapping Supply Chain Management Daily crew huddles
22
ERROR PROOFING - EXAMPLE
25
FIGHTING WASTE - EXAMPLE
26
LEAN ASSEMBLY – 5S + SAFETY Sort…Set…Shine…Standardize…Sustain Cleaner site is safer and more productive
BEFORE
© Walbridge (images)
AFTER
27
LEAN ASSEMBLY – 5S + SAFETY Everything in its place and a place for everything!
(Abdelhamid 2014)
28
REASONS FOR UNMET WEEKLY COMMITMENTS
29
GOLDEN MINE
We have to change what we do to get different results
30
THE PROBLEM - PRODUCTION VARIATION Overburden
Workload Variation
Capability
Waste
Planning Failures
Execution Failures 31
THE SOLUTION - LPS®
Developed by Glenn Ballard & Gregory Howell in 2002 Process design and not only product design LAST PLANNER® SYSTEM (LPS®) ensures:
Reliable commitment Predictable workflows Rapid learning
(Ballard et al, 2002)
32
THE SOLUTION - LPS®
Project Zeneca Ag Products - Building 196 ID
Activity Description
Run Date: Criteria Design Submittals RFI's
Inputs Resources Material Prereq Equipment Labor Weather
Other
Start
Responsible
Demo CMU wall
28-Oct
Cal-Wrecking
Excavate footing
4-Nov
Cal-Wrecking
Install bottom rebar mat
9-Nov
McGrath
X
X
X
X
X
X
X
X
X
X
Install footing dowels
9-Nov
NLB
X
X
X
X
X
X
X
X
X
X
Plumbing rough-in
10-Nov
Perryman
X
X
X
X
X
X
X
X
X
X
Install top rebar mat and stirrups
11-Nov
McGrath
X
X
X
X
X
X
X
X
X
X
Rebar inspection
12-Nov
ICI, C of R
X
X
X
X
X
X
X
X
X
X
Place footing
16-Nov
NLB
X
X
X
X
X
X
X
X
X
X
Install 1st floor wall rebar
19-Nov
McGrath
X
X
X
X
X
X
X
X
X
X
Above sequence
2-Dec
X
X
X
X
X
X
X
X
X
X
Contract X
X
X
X
X
2/21/00 12:57 Comments
Concrete at E-10 must be up to strength.
Possible delay caused by oversized footing.
Total Activities
27
Activities Ready
25
AMR Week - 1 Ratio
92.59%
Make-ready Plan With Constraint Analysis Master & Phase Schedules
Weekly Work Planning 1 WEEK PLAN PROJECT: Pilot ACTIVITY
100%
Gas/F.O. hangers O/H "K" (48 hangers) Gas/F.O. risers to O/H "K" (3 risers) 36" cond water "K" 42' 2-45 deg 1-90 deg Chiller risers (2 chillers wk.)
100%
90%
90%
80%
80%
70%
70%
60%
60%
50%
50%
40%
40%
30%
30%
20%
20%
10%
10%
0%
0%
Est Act Mon xxxx
Tu Wed Thurs Fri xxxx
Sat
Sylvano, Modesto, Terry
xxxx
xxxx
xxxx xxxx
Sylvano, Mdesto, Terry
xxxx
xxxx xxxx
Sun
PPC
Hang H/W O/H "J" (240'-14")
REASON FOR VARIANCES
No Owner stopped work (changing elevations) No Same as above-worked on backlog & boiler blowdown Yes
Charlie, Rick, Ben
xxxx
xxxx xxxx
No
Charlie, Rick, Ben
xxxx
xxxx xxxx
xxxx
xxxx xxxx
xxxx
xxxx xxxx
xxxx xxxx
xxxx
xxxx xxxx
xxxx xxxx
xxxx
xxxx xxxx
No
xxxx xxxx
xxxx
xxxx xxxx
Yes
Matl from shop rcvd late Thurs. Grooved couplings shipped late.
Yes
Mark M., Mike
PPC 4 Week Moving Average
Planning System Measurement
(LCI 2002)
FOREMAN: PHILLIP DATE: 9/20/96
Cooling Tower 10" tie-ins (steel) (2 towers per day) Weld out CHW pump headers "J" mezz. (18) Weld out cooling towers (12 towers)
xxxx
xxxx xxxx
Yes
Steve, Chris, Mark W.
xxxx
Yes
Luke
xxxx Jeff
F.R.P. tie-in to E.T. (9 towers) 50%
xxxx
Eye injury. Lost 2 days welding time
Firt, Packy, Tom
WORKABLE BACKLOG Boiler blowdown-gas vents -rupture disks
33
IMPact FRAMEWORK Prepare
Improve Continuously
Strategize
Plan Operations
Measure
Planning
Reflect, Record, & Communicate
Execute
Execution
34
IMPact FRAMEWORK
(ElSabek 2017)
35
DOMAINS OF PROJECT DELIVERY
CPM-based; Activity-Centered; Management by Exception
Individual craft-contracts
2D/3D
Command & Control Directives-Driven
(Abdelhamid 2014)
36
DOMAINS OF PROJECT DELIVERY
CPM-based; Activity-Centered; Management by Exception
Lean-based; Management by Means Individual (planning inclusive of execution party; fire prevention) craft-contracts
2D/3D BIM/VDC
IPD/IFOA Relational (system optimization)
Command & Control Directives-Driven Dialogue & Collaboration (Abdelhamid 2014)
(planning is an ongoing conversations) 37
LEAN PROJECT DELIVERY SYSTEM (LPDS)
Lean Project Delivery System (Ballard, 2006) 38
CULTURE OF LEAN CONSTRUCTION
Problems are recognized as opportunities
It’s okay to make legitimate mistakes
Problems are exposed because of increased trust
People are not problems – they are problem solvers
Emphasis is placed on finding solutions instead of “who did it”
39
THE RADICAL SHIFT Planning Scheduling Control Focus Organizational Behavior Coordination Site Management Management Design
Non-Lean
Lean
Knowledge
Learning
“Start Early” Activities are performed as soon as possible
“Finish Early” Activities are performed at the last responsible moment
Tracking & Reacting
Peering, Clearing, Steering
Acceleration
Reliability
Managers are empowered
Executers are the planners Collaboration, Respect, and Trust
Follow Orders
Making & Keeping Promises
Point Speed & 100% Utilization
Manage workflow
Trades Cost for Speed
Reduce Cost and Increase Speed
Project Design
Process Design
Lean Construction Institute - www.leanconstruction.org
40
BENEFITS OF LEAN CONSTRUCTION
McGraw Hill 2013
41
SUCCESS STORIES Temecula
Valley Hospital 2013
$700
million project 40% below market cost Realized 200% increase in labor productivity through the 7 partners 30% operational cost improvement in the facility
Sutter Health ( $5 billion program) 42
SUCCESS STORIES
“If we can get the construction community to embrace these methodologies, it will make every person perform their jobs better. And I think that’s exciting. It will make us better, more efficient, and probably more profitable” Dan Wojtkowski, network director for design and construction – SSM Healthcare
"First, Lean is simply systematically applied common sense. Second, it is counterintuitive. Unlike anything I've seen before, it causes us to rethink how we manage work. And, finally we saw it as an opportunity to deliver high value facilities to the marketplace in shorter time." Paul Reiser, Boldt‘s Vice president for Production Process Innovation "Lean lowers the 'hairon-fire' index on our jobs." Linbeck Construction
43
LEAN CONSTRUCTION IN QATAR
Implemented in 3 pilot projects at Lusail City
Adapted by PWA in March 2018
44
Roads: 11,400 m 15 junctions Underpasses: 1,018 m and 440 m Utility tunnel (cut & cover): 3,200 m Potable water pipes: 16,583 m Foul sewer pipes: 5,090 m Stormwater pipes: 34,761 m Irrigation pipes: 17,085 m
CP5B Case Study (LPS ®) JP 1
J1
JR 1
JP 2
JP 4
UNDERPASS 2
JP 5
Cost: QAR 1.5 bn Excavation: 1,800,000 mᴲ Pavement: 1,000,000 m² Concrete: 380,000 mᴲ
JP UNDERPASS 1 6
J5
45
Road A1, Section 2, Jct 5
Junction 5
46
Site Photos
47
Prepared & Delivered by Aqib Rizvi
Site Photos
48
Revisions of Master Baseline Schedule
Revision Number
Project Commencement Date
January 15, 2012
Original Completion Date
July 14, 2014
Revision 5 Completion Date
March 31, 2017
Original Project Duration
912
Revision 5 Project Duration
1903
Date of Submission
Date of Approval
Completion Date
Remarks
Revision 0
22-Mar-2012
16-Apr-2012 14-Jul-2014 First Baseline submission incorporating original contract parameters.
Revision 1
11-Jul-2012
4-Sep-2012
Revision 2
28-Feb-2013
21-Mar-2013 14-Jul-2014 In 2nd revision, GC trying to recover in response to schedule slippage
Revision 3 (EOT 1)
10-Jul-2014
5-Aug-2014 31-Dec-2014 Approved with comments. 3rd revision incorporated excusable delay events that resulted in 170 days extension of time (EOT 1)
14-Jul-2014 Approved with comments. 1st revision of the schedule was submitted 3 months after Rev. 0 approval due to major delays in mobilization
Start of LPS® Case Study: Milestone I (30-Oct-2014) & Milestone II (01-Mar-2015) Revision 4 (EOT 2)
15-Jul-2015
Revision 5 (EOT 3)
7-Aug-2016
15-Dec-2015 25-Mar-2016 Due to lengthy disagreement, completion date of Rev. 3 elapsed by 285 days before Rev. 4 was granted EOT 2 with additional 450 days 17-Jan-2017 31-Mar-2017 5th revision incorporated excusable delay events with an additional 371 days to the Completion Date. 49
PPC Results of the 1st Application 01-11-14
Start week Company Logo
W1 W2
Week J2 J2-J3
W3
W4
W5
W6
W7
W8
95 100
73 75
51 67
62 64
75 67
100 83
100 100
100 100
Project
CP5B Road Construction
J1-GD1
40
60
25
30
0
83
63
100
Location
VIP Road (December 31, 2014)
JP1/JP2
100
67
63
25
57
75
100
100
JP5-UP1
71
58
50
21
50
88
100
100
Percent Planned Complete (PPC)
J2 100
100
67
60 100
95
80
100 100
100 83
80
67
60
60
40
40
20
20
0
0
40
63
25
30 0
JP1/JP2
51 100 80 60 0
100
62
60
20
64
100 100
75
73
40
83
75
80 120
J1‐GD1
J2‐J3
100
100
100 100 75
67 57
63
0
25
100
100 80 60 40
40 20
JP5‐UP1
20
88
71
100
58 50
50 21
0
50
PPC Results of the 2nd Application 11-6-15
Start week Week JP6 J5
W1 100% 100%
W2
W3
100% 100%
90% 20%
W4 89% 67%
W5 56% 20%
W6 40% 33%
W7
W8
52% 43%
62% 51%
W9 89% 89%
W10 89% 89%
W11
W12
76% 95%
56% 93%
W13 60% 94%
W14 76% 93%
W15 89% 95%
Project
CP5B Road Construction
FH1
80%
86%
100%
22%
30%
62%
81%
97%
78%
78%
79%
78%
80%
91%
95%
Location
Road Completion (June 30, 2015)
FH2
100%
100%
67%
40%
33%
65%
85%
95%
94%
94%
100%
100%
100%
97%
97%
FH3
100%
100%
75%
75%
25%
50%
65%
78%
75%
75%
100%
100%
100%
100%
100%
J3
100%
100%
100%
100%
78%
60%
50%
60%
33%
33%
29%
67%
67%
73%
73%
J4
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
73%
67%
62%
77%
95%
Percent Planned Complete (PPC)
120% 100% 80%
FH1
J5
JP6 120%
120%
100%
100%
80%
80%
60%
60%
40%
40%
20%
20%
0%
0%
60% 40% 20% 0%
J3
FH3 120%
120%
100%
100%
80%
80%
60%
60%
40%
40%
20%
20%
0%
0%
FH2
J4
120%
120%
100%
100%
80%
80%
60%
60%
40%
40%
20%
20%
0%
0%
51
LPS ® Implementation
52
LPS ® Implementation
53
Prepared & Delivered by Aqib Rizvi
LPS ® Implementation
54
5G CASE STUDY – FIGHTING WASTES
55
5G CASE STUDY – FIGHTING WASTES
56
CASE STUDY RESULTS
Saving in 66 kV circuits of 4,500 m (13,500 m of cables). Deletion of approximately 800 m of dry utility tunnel (which could have been 1,000 m) Hard Saving of approximately QAR 100,000,000 (excluding operation cost saving) Triggered further Saving of approximately QAR 100,000,000
57
INSPIRING QUOTE
58
QUESTIONS
https://www.linkedin.com/in/luai-m-sabek-phdpe-peng-pmp-cm-lean-3a7b3911/ Email: [email protected] 59
THE LEAN CONSTRUCTION INSTITUTE‐ QATAR Transforming The Built Environment
Dawlat M. Elmosalami, Msc., PMP Marketing Executive Director
INSPIRATION "We have taken advantage of the drop in prices to explore the potential for rationalizing spending, and distinguishing necessary from unnecessary as well as beneficial from non‐beneficial. Work will continue on increasing the efficiency of public spending and enhancing transparency and control through a close follow‐up of all government projects and programs and focusing on major development projects. •
His highness focused on the need to: •
•
Identifying the obstacles that hampered the implementation of some programs and projects in the first national development strategy to draw lessons in order to avoid recurrence. Maintaining the required continuity to complete the initiatives and infrastructure projects. The opening of the 45th Session of
LCI‐Q Alignment with 2nd National Development Strategy 2018‐2022
Focusing on human beings as the development tool “I would like to emphasize here that plans are not a matter of completing a formality; they are designed to be implemented.” Integrated monitoring and follow-up system Prevent bottlenecks and take necessary corrective actions on a timely basis.
Abdullah bin Nasser Al Thani Prime Minister
Maximizing real private public partnerships (PPP). Financial sustainability (increased efficiency) Improving coordination and communication among all development partners; Building planning capacity and upgrading performance reduce loss of efforts, resources and time. Optimal response to the current sanctions against Qatar Maximizing the values of work and achievement.
Dr. Saleh bin Mohamed Al Nabit Minister of Development Planning and Statistics
INTRODUCTION • Lean Construction Institute in USA is the world’s largest organization for Lean Construction. • LCI-Q is the first global Lean community of practice in: GCC Arabic Countries Asia and North Africa • Nonprofit organization • Registered under Qatar Financial Center Authority since October 10, 2019
VISION • Promoting the Lean Construction theory, management, practices, and techniques throughout Qatar. • Supporting continuing positive transformation of Construction industry to enhance performance, generate value, eliminate waste, increase efficiency, and maximize productivity. • Providing a platform for collaboration across industry and academia.
MISSION • Spread awareness of Lean Construction and Lean Thinking in Qatar. • Provide the best opportunities to local Lean Construction management professionals and academics who are seeking genuine education, research, training, conferences, knowledge, and networking. • Establish a platform to share experience, knowledge, lessons learned, and best practices. • Promote Lean Thinking. • Supporting the State of Qatar’s 2030 Vision, realizing human development, social development, economic development, and environmental development; by developing businesses and Qatari nationals in the field of engineering and construction management.
LCI-Q Current Sponsors Platinum Founding Sponsors
Gold Sponsors
Bronze Sponsors
COLLABORATING PARTNERS
LEAN THINKING IN QATAR • Implemented in 3 pilot projects at Lusail City • Hard Saving: QAR 200 million • Adapted by PWA since March 2018 • Major Financial Institutions • Qatar Airways • Health Care • Oil & Gas • Manufacturing
PAST EVENTS • “Recognizing Lean Transformation in Public Sector - LIPS Qatar 2019” in collaboration with Public Works Authority and Qatar University, October 23 & 24, 2019 Attended by over 220 delegates
Platinum Sponsors
• AGC LCEP Program LCI-Q trained the first group to qualify for Certificate of Management-Lean Construction (CM-Lean) under the Lean Construction Education Program of Associated General Contractors of America (AGC). October 26 - 30, 2019.
• Inauguration Event December 11, 2019 Attended by over 200 delegates
Gold Sponsors
PAST EVENTS Seminar with Jordan Engineers Association “Fundamentals of Lean Construction” Date: January 25, 2020 Time: 8:00 am – 2:00 pm Venue: The Great Room - W Doha Hotel
UPCOMING EVENTS International Conference on Civil Infrastructure and Construction (CIC) Date: February 2 - 5, 2020 Time: TBD Venue: Grand Hyatt Hotel
AGC LCEP Program Date: Saturdays Cycle 1: February to June Cycle 2: September to December Venue: TBD
PLAN TO CREATE LEAN LEADERS • Conferences and Workshops • Training and Education Programs • Lean in Schools: Pilot (Michael E. DeBakey High School) • Action Research • Site Visits • Lean Practice Day • Lean Marathon • Lean Coffee • Lean Thinker Award
JOIN THE TRANSFORMATION JOURNEY!
[email protected] www.LCI.QA