ITEM Descripción Parciales Primer mes (30 días) 1era semana 1 OBRAS PROVISIONALES 2 OBRAS PRELIMINARES 7,823.61
Views 112 Downloads 1 File size 169KB
ITEM
Descripción
Parciales
Primer mes (30 días)
1era semana
1
OBRAS PROVISIONALES
2
OBRAS PRELIMINARES
7,823.61
3
MOVIMIENTO DE TIERRAS
12,086.47
4
PAVIMENTOS
129,654.61
2da Semana
3ra Semana
SEGUNDO MES (30 DÍAS)
4ta semana
5ta semana
6ta semana
7ma semana
8va semana
2,833.72 1700.23
1133.49
7823.61 2417.3
7251.88
2417.29 25930.93
5 6 7
SARDINELES VEREDAS VARIOS
Total del costo directo Gastos generales 10% Sub-Total I.G.V.19% Total presupuesto
25930.92
25930.92
25930.92
25930.92
6661.53
6661.53
3330.77
12747.25
6863.90
16,653.83 19,611.15 2,811.49 191,474.88 19,147.488 210,622.37 40,018.25 250,640.62
11941.14 1194.11 13135.25 2495.70 15630.95
7251.88 725.19 7977.07 1515.64 9492.71
28348.22 2834.82 31183.04 5924.78 37107.82
25930.92 2593.09 28524.01 5419.56 33943.57
32592.45 3259.25 35851.70 6811.82 42663.52
45339.7 4533.97 49873.67 9476.00 59349.67
36125.59 3612.56 39738.15 7550.25 47288.40
2811.49 3944.98 394.50 4339.48 824.50 5163.98