AJUSTE DE PRECIOS UNITARIOS 1.- MANO DE OBRA - REVISAR INCIDENCIA DE CARGOS (%) - REVISAR % APORTES EMPLEADOS Y BENEFICIOS SOCIALES - INCLUIR CARGOS O PUESTOS NO CONTEMPLADOS - REVISAR ALGUNOS JORNALES Y AJUSTAR TARIFAS HORARIAS

2.- MATERIALES - INCLUIR MATERIALES NO CONTEMPLADOS - REVISAR TIEMPO DE VIDA ACEROS (OK) - ACTUALIZAR PRECIO DE MATERIALES

3.- EXPLOSIVOS (NO INCLUIR) - REVISAR CONSUMO DE EXPLOSIVOS (ESTANDARES DE VOLADURA)

4.- EPP'S Y HERRAMIENTAS - REVISAR % DE INCIDENCIA DE MANO OBRA

5.- EQUIPOS - REVISAR TARIFA HORARIA SCOOP'S Y JUMBOS (CON MUCHO CUIDADO)

6.- ADICIONAL - CONSIDERAR EXCAVACION DE CUNETA

7.- UTILIDAD - REVISAR MARGEN DE UTILIDAD (IESA = 26,28% Y MVC 25.00%)

8.- COMPARACION LABOR PU IESA 4,5 X 4 (-) 519.66 4,5 X 4 (+) 484.13 4 X 4 (+) 461.57

PU MVC DIFERENCIA 335.8 183.86 308.88 175.25 300.58 160.99

% 55% 57% 54%

MATERIALES MODIFICACION DE PRECIO COMPRA DE MATERIALES INCLUIDOS ($) MATERIAL Barras de perforacion 12' Brocas de 51 mm Shank Adapter Coopling Rimadora de 89 mm Adapter piloto Copas de Afilado Aguzadora de copas Barrenos integrales (cancamos) Barrenos integrales (cuneta) Mangas de Ventilacion 24" Cancamos Manguera de 2" ( 100 m) Manguera de 1" ( 100 m)

UM UND UND UND UND UND UND UND UND UND UND MTL UND MTL MTL

PRECIO PU 150.00 57.00 135.00 33.00 183.00 175.00 110.00 1,600.00 78.00 62.83 1.00 1.00 8.00 1.49

PRECIO REAL 320.00 95.00 300.00 68.62 210.00 215.00 110.00 1,600.00 106.00 81.00 2.49 4.00 15.00 4.50

UM GLN KG UND MTL MTL MTL UND

PRECIO ($) 5.71 1.40 35.00 47.00 30.00 10.00 1.45

CANTIDAD 0.20 0.10 0.05 0.15 0.19 1.00 6

DIFERENCIA %PU/REAL 170.00 47% 38.00 60% 165.00 45% 35.62 48% 27.00 87% 40.00 81% 100% 100% 28.00 74% 18.17 78% 1.49 40% 3.00 25% 7.00 53% 3.01 33%

MATERIALES NO INCLUIDOS ITEM ACEITE DE PERFORACION ALAMBRE NEGRO REFLECTORES CABLE PARA JUMBO MANGUERA TIPO BOA 4" MANGA DE VENTILACION 36" TUBO PVC

EPP'S Y HERRAMIENTAS MODIFICAR % DE MANO DE OBRA EN INCIDENCIA DE EPP'S Y HERRAMIENTAS TIPO EMPLEADO IMPLEMENTOS DE SEGURIDAD HERRAMIENTAS

% PU 5.00% 5.00%

% PROPUESTO 8.00% 5.00%

TIEMPO DE VIDA DE VARRILAJE MATERIAL Barras de perforacion 12' Brocas de 51 mm Shank Adapter Coopling Rimadora de 89 mm Adapter piloto

UM UND UND UND UND UND UND

T. VIDA PU 10,000.00 4,317.00 13,123.00 4,921.00 1,500.00 1,640.00

T.VIDA REAL 10,000.00 2,400.00 20,000.00 20,000.00 4,500.00 4,500.00

ENERO 8,680.55 3,255.20 30,381.91 30,381.91 4,087.58 4,087.58

FEBRERO 7,518.92 2,506.31 36,090.81 36,090.81 3,678.71 3,678.71

MARZO 7,812.39 2,050.75 20,507.52 20,507.52 1,283.22 1,283.22

ABRIL 8,577.79 2,075.27

5,660.55 5,660.55

TIEMPO DE VIDA - 2008 MAYO JUNIO 13,684.30 10,060.07 2,359.36 2,690.48 20,526.45 25,709.07 20,526.45 25,709.07 4,665.25 6,819.15 4,665.25 6,819.15

JULIO 11,183.71 3,035.58 26,561.32 26,561.32 4,812.00 4,812.00

008 AGOSTO 12,045.91 2,269.52 15,659.68 15,659.68 6,807.15 6,807.15

SETIEMBRE 12,787.25 2,841.61 29,836.93 29,836.93 7,426.07 7,426.07

PROM. 01 10,261.21 2,564.90 25,659.21 25,659.21 5,026.63 5,026.63

PROM. REAL PU 10,000.00 10,000.00 2,400.00 4,317.00 20,000.00 13,123.00 20,000.00 4,921.00 4,500.00 1,500.00 4,500.00 1,640.00

PERSONAL CARGOS NO INCLUIDOS PUESTO

INCIDENCIA JORNAL (S/.)

MECANICO ELECTRICISTA TOPOGRAFO AY. TOPOGRAFO DIGITADOR A. RESIDENTE

10% 10% 20% 40% 10% 10%

57.00 57.00 83.33 62.00 23.33 183.33

MODIFICAR INCIDENCIA DEL TRABAJADOR Y JORNAL

PUESTO

PU

Jumbero Ayudante de Jumbero Operador de Scoop Cargadores disparadores Ayudantes Estándares Bombero poza principal Tubero Ventilación Desatador Capataz Bodeguero Tecnico de Voladura Jefe de Guardia

INCIDENCIA PROPUESTO 50% 50% 50% 50% 50% 35% 10% 10% 10% 33% 20% 0% 33%

50% 50% 50% 50% 50% 35% 20% 20% 20% 33% 20% 0% 33%

PU 57.00 42.00 52.00 42.00 42.00 47.00 42.00 42.00 42.00 67.00 47.00 83.33 166.67

JORNAL (S/.) PROPUESTO DIFERENCIA 67.00 42.00 62.00 42.00 42.00 47.00 42.00 42.00 42.00 67.00 47.00 83.33 166.67

MODIFICAR % GLOBAL DE APORTES DE EMPLEADOR Y BENEFICIOS SOCIALES TIPO EMPLEADO EMPLEADOS OBREROS

% PU 57.61% 93.35%

% REAL 77.20% 108.23%

-

10.00 10.00 -

EQUIPOS (Con cuidado) MODIFICAR LA TARIFA HORARIA DE EQUIPOS ($) TIPO EQUIPOS JUMBO SCOOP

PU 54.77 51.59

PROPUESTO 59.00 54.89

-

DIFERENCIA 4.23 3.30

ITEM ADICIONAL INCLUIR EN EL PU EXCAVACION DE CUNETA 0,5X0,5M COSTO POR ML ($)

23.95

UTILIDAD MODIFICAR % DE UTILIDAD ITEM UTILIDAD

% PU 25.00%

% PROPUESTO 26.28%